- Asked by: Tim Eagle, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 12 July 2024
-
Current Status:
Answered by Fiona Hyslop on 7 August 2024
To ask the Scottish Government by what date the MV (a) Isle of Islay and (b) Loch Indaal will be fully operational.
Answer
The planned in-service dates provided by CMAL in the June 2024 update to the NZET Committee were end November 2024 for MV Isle of Islay and end March 2025 for MV Loch Indaal.
Transport Scotland, CMAL and CalMac will keep these dates under review as the vessel builds progress. The dates will be subject to successful completion of construction, now entering the complex systems commissioning phases, and further crew familiarisation and berthing trails upon arrival in Scottish waters.
Further updates will be provided to Parliament in due course.
- Asked by: Fergus Ewing, MSP for Inverness and Nairn, Scottish National Party
-
Date lodged: Monday, 15 July 2024
-
Current Status:
Answered by Fiona Hyslop on 7 August 2024
To ask the Scottish Government, regarding the advanced works for the dualling of the A9 between Tomatin and Moy, whether it will provide a detailed breakdown of the (a) total cost and (b) cost of any (i) preparatory work and (ii) consultancy fees for the creation of an ecological pond to accommodate a fly species.
Answer
Advance works to a cost of £22.6 million have been undertaken for the A9 Dualling: Tomatin to Moy project, to de-risk the main construction works contract.
This cost is broken down as follows:
A9 Dualling: Tomatin to Moy Advance Works | Final Cost |
Archaeological Investigation | £0.6m |
Tomatin Distillery Advance Worksand Local Road Improvements Project | £1.5m |
Ground Investigation Works 2016-2022 | £9.5m |
Network Rail Lynebeg Underbridge Advance Works | £10.5m |
Intelligent Transport System Advance Works (Variable Message Signs and CCTV) | £0.5m |
Total | £22.6m |
The figures above are exclusive of land acquisition costs and design fees.
The Lynbeg Railway Underbridge advance works contract included construction of a new ecological pond to support local ecology, including a nationally rare sub-species of the Caddisfly, which is encountered at only nine locations in the UK, including Lynebeg. The new ecological pond was constructed to meet the commitments set out in the Environmental Statement for the Tomatin to Moy project, specifically Mitigation Items P12 to W32 and P12 to E31, found on pages 21 to 42 and 21 to 50 of the Environmental Statement respectively. The new pond was constructed during the Lynebeg Railway Underbridge advance works contract to de-risk the programme impact on the main works contract.
The cost information available does not enable a breakdown of costs to be provided in the exact form requested.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 15 July 2024
-
Current Status:
Answered by Natalie Don on 7 August 2024
To ask the Scottish Government, further to the answer to question S6W-27078 Natalie Don on 9 May 2024, in which it indicated its expectation that data on the scale, uptake and delivery models of breakfast provision across Scotland, both at local authority and schools' level, would be submitted to the Scottish Government in June 2024, whether it has received this data, and, if this is not the case, what the reasons are for the delay in the data being provided, and when the Scottish Government will report on the next stages.
Answer
The Scottish Government has been working with AssistFM and Improvement Service to map existing breakfast provision across Scotland, including a survey to all primary and special schools to understand the scale and uptake of provision.
A report with the findings from the mapping exercise was submitted to the Scottish Government in June 2024. The findings are being used to inform the government’s approach and we will report any decisions made about next steps once the data has been fully considered.
- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 22 July 2024
-
Current Status:
Answered by Fiona Hyslop on 7 August 2024
To ask the Scottish Government what assessment has been made of any impact on small businesses of the introduction of restricted pavement parking.
Answer
During the development of the Transport (Scotland) Act 2019, which brought in the ban on pavement parking, Transport Scotland convened a Parking Standards Group to seek views on the policy. This group comprised of a wide range of key stakeholders, including the Federation of Small Businesses.
This group continued to meet during the evolution of the Act, along with the development of secondary legislation that was required to bring the ban into force. No concerns were raised by the Federation of Small Businesses during this process. A number of consultations were undertaken throughout this period and no concerns were highlighted regarding small businesses, either from the Federation of Small Businesses or any other parties.
Particular consideration was given to small businesses during the development of the Act which allows for a 20 minute exception for goods to be loaded or delivered, where 1.5 metres of clear pavement is left for the passing of pavement users.
Furthermore, statutory Business and Regulatory Impact Assessments were carried out for each piece of legislation and no impacts to small businesses were identified.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Wednesday, 17 July 2024
-
Current Status:
Answered by Fiona Hyslop on 7 August 2024
To ask the Scottish Government, in light of the announcement on 16 July 2024 regarding Phase 1 of the Small Vessel Replacement Programme, whether it will apply a social value weighting to the procurement procedure that is sufficient to ensure that the construction of the vessels is carried out in Scotland.
Answer
CMAL, as the procuring authority, has highlighted that Scottish public procurement regulations explicitly state that contracting authorities cannot artificially narrow competition by designing a procurement with the intention of unduly favouring, or disadvantaging, any particular economic operator. This means that CMAL cannot lawfully weight or design the contract requirements to favour Scottish shipyards or businesses. All candidates must be treated equally and fairly.
- Asked by: Monica Lennon, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 19 July 2024
-
Current Status:
Answered by Fiona Hyslop on 7 August 2024
To ask the Scottish Government, in light of the 2022 Transport Scotland report, Reducing car use for a healthier, fairer and greener Scotland, what progress is being made in developing its car-kilometre reduction strategy that will set out set out how it will achieve a reduction in car-kilometres and deliver "20-minute neighbourhoods", where people can have their everyday needs met locally within a 20-minute walk, wheel or cycle from their homes, and by what date this strategy will be published.
Answer
Publication of the 20% car use reduction route map is planned in autumn this year. It is being produced in partnership with CoSLA.
On 25 April 2024 planning guidance on local living and 20 minute neighbourhoods was published, setting out a framework and information on how the concepts of local living and 20 minute neighbourhood can be applied in a Scottish context, as set out in the fourth National Planning Framework.
The above-mentioned route map does not commit to delivering 20 minute neighbourhoods, although both policies mutually support each other.
- Asked by: Ariane Burgess, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Friday, 26 July 2024
-
Current Status:
Answered by Kaukab Stewart on 7 August 2024
To ask the Scottish Government, in light of the potential impact on people in Scotland who are refugees, whether it has made representations to the UK Government to publish a national integration strategy that promotes more equal support for all displaced people and builds on learning across each of the four UK nations.
Answer
Scotland’s national refugee integration strategy has been in place for over a decade. In March 2024 the third New Scots refugee integration strategy was published. It is a UK-leading integration approach built on a partnership led by the Scottish Government, COSLA and Scottish Refugee Council. It was informed by an engagement process involving over 2,000 refugees and people seeking asylum. The strategy is accompanied by a delivery plan setting out the actions that New Scots partners will undertake to deliver the strategy. We hope that other governments can learn from our work.
Scottish Ministers have held introductory calls with their new UK Government counterparts and we look forward to working closely with the UK Government to support delivery of a more effective and humane asylum system and resettlement schemes. We are not aware of any plans, however, to publish a UK integration strategy.
- Asked by: Ariane Burgess, MSP for Highlands and Islands, Scottish Green Party
-
Date lodged: Friday, 26 July 2024
-
Current Status:
Answered by Kaukab Stewart on 7 August 2024
To ask the Scottish Government what steps it is taking to help displaced people across the private rented sector.
Answer
I refer the Member to the answer to question S6W-28627 on 31 July 2024.
All answers to Parliamentary Questions are available on the Parliament’s website, the search facility for which can be found at http://www.parliament.scot/chamber-and-committees/questions-and-answers .
- Asked by: Oliver Mundell, MSP for Dumfriesshire, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 25 July 2024
-
Current Status:
Answered by Ivan McKee on 7 August 2024
To ask the Scottish Government for what reason additional grid capacity and infrastructure at Bearholm substation has reportedly been granted planning permission, in light of the Rivox and Scoop Hill Windfarm planning applications reportedly having not yet been determined.
Answer
The decision to grant planning permission for an extension to an existing substation at Bearholm near Moffat was made by the relevant planning authority, Dumfries and Galloway Council.
Planning authorities are required to determine any valid application submitted to them in accordance with the relevant local development plan and National Planning Framework 4 (NPF4) unless there are material considerations which justify a departure from the plan. The decision notice of the authority is required to include the reasons for the decision. In addition, as part of the decision-making process the authority is required to produce a report setting out their consideration of the application and the material considerations taken into account. The decision notice and report are published on the planning authority’s website.
Applications for consent for the Rivox Wind Energy Hub and Scoop Hill Community Wind Farm projects are currently with the Scottish Ministers for determination under section 36 of the Electricity Act 1989.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Thursday, 18 July 2024
-
Current Status:
Answered by Fiona Hyslop on 7 August 2024
To ask the Scottish Government for what reason it has divided the Small Vessel
Replacement Programme into phases, and what its position is on whether a series
production approach for all vessels in the programme would (a) enable the
maximisation of any learning curve efficiencies and (b) incentivise capital
investment in shipyard productivity.
Answer
Careful consideration was given to the most efficient phasing of the Small Vessel Replacement Programme. This resulted in the current split with seven similar vessels procured in the first phase.
Phase two of the programme takes in other routes in the Clyde and Hebrides Ferry Service network where the service requirements differ from the seven vessels in phase one, including routes where specific requirements need to be addressed. CMAL will be commencing with studies and engagement on these vessels later this year.