- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 27 January 2022
Submitting member has a registered interest.
-
Current Status:
Answered by Shona Robison on 9 February 2022
To ask the Scottish Government what engagement it has had with the Scottish Law Commission in relation to carrying out a law reform project to provide a draft Bill that would implement the recommendations of the Scottish Parliamentary Working Group on Tenement Maintenance.
Answer
The Scottish Government has issued a letter to the Scottish Law Commission on 10 January 2022, commissioning a Law Reform Project to provide a draft Bill that would implement the recommendations of the Scottish Parliamentary Group on Tenement Maintenance.
- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 27 January 2022
-
Current Status:
Answered by Lorna Slater on 9 February 2022
To ask the Scottish Government how many times civil servants met, including virtually and in person, operators of deposit return schemes, broken down by (a) when the meetings took place and (b) which operators were involved, between 16 March 2020 and 14 December 2021.
Answer
Officials did not have any meetings with operators of overseas deposit return schemes (DRS) in the time period specified.
Evidence from other international schemes has played an important role in our decision-making regarding Scotland’s Deposit Return Scheme (DRS) and operators of other schemes provided advice to Zero Waste Scotland during the policy-design process. During our review of the implementation date for DRS, Deloitte LLP has provided expertise and independent assurance relating to the process of establishing a scheme administrator, including drawing on its experience as an advisor to other operators and the wider global DRS network.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 27 January 2022
-
Current Status:
Answered by Richard Lochhead on 9 February 2022
To ask the Scottish Government, further to the answer to question S6W-05226 by Richard Lochhead on 18 January 2022, when it expects to set the objectives and key deliverables for the Just Transition Fund (a) in year 1 (2022) and (b) for the first tranche of £20 million of funding, and when the referenced "programme of engagement" will conclude.
Answer
There is no distinction between objectives and deliverables of the £500 million Just Transition Fund for year one, and the £20 million allocation for year one.
Detailed policy design work and implementation planning, supplemented by a programme of engagement, is underway ahead of the new financial year. This will inform the objectives and deliverables of the Just Transition Fund. Further updates will be shared as this engagement develops. We will work collaboratively, continuing to engage and co-design this Fund with partners in region throughout the lifetime of this ten-year £500 million commitment to the North East and Moray.
- Asked by: Alexander Burnett, MSP for Aberdeenshire West, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 27 January 2022
-
Current Status:
Answered by Kate Forbes on 9 February 2022
To ask the Scottish Government whether it will provide an update on its engagement with the UK Government on the delivery of the Project Gigabit scheme in Scotland.
Answer
The Scottish Government is currently working closely with Building Digital UK (BDUK) to develop our understanding of what Project Gigabit means for Scotland. To date, Project Gigabit has primarily focussed on England with the procurement approach developed for the supplier market there. We want to be sure that any approach works in a Scottish context and is tailored to extend future-proofed digital connectivity across the country.
We hope to publish a Gigabit Open Market Review in the coming weeks which will inform any future gigabit procurement strategy for Scotland. We want to ensure that Scotland receives a fair share of Project Gigabit funding and support – a share commensurate with the scale of the challenge we face.
- Asked by: Sharon Dowey, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 26 January 2022
-
Current Status:
Answered by Ben Macpherson on 9 February 2022
To ask the Scottish Government by what date the roll-out of the increased Scottish Child Payment will be complete.
Answer
I refer the member to the question S6W-05691 on 9 February 2022. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers .
- Asked by: Sharon Dowey, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 26 January 2022
-
Current Status:
Answered by Ben Macpherson on 9 February 2022
To ask the Scottish Government whether a letter of comfort has been provided by the Department for Work and Pensions (DWP) regarding the delivery of the roll-out of the increased Scottish Child Payment, as referred to in the minutes from the 17th meeting of the Joint Ministerial Working Group on Welfare from November 2021.
Answer
I have received a response from Chloe Smith, the Minister for Disabled People, Health and Work, to my letter of 5 January 2022 on the delivery of the roll-out of the extension of Scottish Child Payment to 6-15 year olds. That response confirms the Department for Work and Pensions’ commitment to “an agreed approach to the provision of the data which supports [the Scottish Government’s] proposed delivery timeline”.
That timeline is that the extension of Scottish Child Payment to 6-15 year olds will begin from the end of 2022.
The strong preference of the Scottish Government has consistently been to extend the existing interfaces, which are currently in place to support delivery of the Scottish Child Payment for under 6s, but the DWP’s position is that we should build to align with their new strategic solution. This carries a higher degree of risk to our delivery timeline, as the DWP’s new strategic solution is still in the design phase, but we have an agreed joint plan in place to monitor and track that risk.
Our officials continue to work closely to ensure the implementation of the required technical approach and Ministers will meet in due course to review progress.
- Asked by: Alex Rowley, MSP for Mid Scotland and Fife, Scottish Labour
-
Date lodged: Tuesday, 25 January 2022
-
Current Status:
Answered by Shona Robison on 9 February 2022
To ask the Scottish Government, further to the ministerial statement on strengthened fire alarm standards on 19 January 2022, what estimates it has made of the number of homes that will (a) comply and (b) not comply with the new legislation on interlinked fire alarms by 1 February 2022.
Answer
Once the new standard comes into force, the Scottish Government will collect data on fire alarms in Scottish homes in future iterations of the Scottish House Condition Survey. Following the Scottish Government’s mass media awareness campaign in 2021, we know there are high levels of awareness and home-owners will have taken steps to fit the necessary alarms.
Information on the number of homes that have interlinked fire alarms is not currently collected as part of the Scottish House Condition Survey. This standard has already applied to private rented homes and new build homes for over a decade. Social landlords also have a programme of works underway to ensure their tenants have the necessary alarms fitted.
- Asked by: Alex Rowley, MSP for Mid Scotland and Fife, Scottish Labour
-
Date lodged: Friday, 21 January 2022
-
Current Status:
Answered by Jenny Gilruth on 9 February 2022
To ask the Scottish Government what its position is on whether reducing 300 rail services from pre-pandemic levels will increase or decrease rail passenger numbers.
Answer
ScotRail’s May 2022 timetable, benefiting from careful consideration of the consultation feedback, is significantly better than the May 2021 timetable, with 150 more services per day. The aim is to build weekday passenger capacity to more than 590,000 seats, ensuring ScotRail Trains Ltd operate a more sustainable and more robust financial footing.
- Asked by: Douglas Lumsden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 09 December 2021
-
Current Status:
Answered by Kevin Stewart on 8 February 2022
To ask the Scottish Government what proportion of the Mental Health Transformation Fund has been allocated to each NHS board in each year since 2018.
Answer
The information requested is shown in the following table for 2018-19 to 2020-21, the latest complete financial year available.
Data for 2020-21 demonstrates that NHS Board allocations slightly exceeded the original planned budget, the balance of which was off-set by other mental health programme budgets.
Table - Proportion of Mental Health Transformation Budget Allocated to NHS Boards in 2018-21 | Proportion of Budget allocated to NHS Board in 2018-19 | Proportion of Budget allocated to NHS Board in 2019-20 | Proportion of Budget allocated to NHS Board in 2020-21 |
NHS Ayrshire & Arran | 4% | 4% | 4% |
NHS Borders | 2% | 0% | 2% |
NHS Dumfries and Galloway | 2% | 2% | 2% |
NHS Fife | 4% | 4% | 4% |
NHS Forth Valley | 3% | 3% | 3% |
NHS Grampian | 5% | 5% | 5% |
NHS Greater Glasgow and Clyde | 12% | 9% | 11% |
NHS Highland | 4% | 4% | 3% |
NHS Lanarkshire | 8% | 8% | 7% |
NHS Lothian | 9% | 8% | 7% |
NHS Orkney | 1% | 1% | 1% |
NHS Shetland | 1% | 1% | 1% |
NHS Tayside | 4% | 4% | 4% |
NHS Western Isles | 1% | 1% | 1% |
NHS Education for Scotland | 22% | 30% | 33% |
NHS Health Improvement Scotland | 4% | 5% | 1% |
NHS Health Scotland/Public Health Scotland | 0% | 0% | 2% |
NHS National Services Scotland | 1% | 1% | 4% |
NHS 24 | 0% | 0% | 8% |
TOTAL | 87% | 90% | 101% |
- Asked by: Christine Grahame, MSP for Midlothian South, Tweeddale and Lauderdale, Scottish National Party
-
Date lodged: Thursday, 03 February 2022
-
Current Status:
Answered by Humza Yousaf on 8 February 2022
To ask the Scottish Government what the advice is for choirs in relation to COVID-19; (a) whether and (b) when face coverings should be used during rehearsals and performances with social distancing, and (i) whether and (ii) when social distancing should be maintained during rehearsals and performances.
Answer
The approach to face coverings for choirs is grounded in evidence and draws on the expert advice which reflects the unique features of the activity and the environments. This is because the virus spreads when an infected person talks, sings or even breathes heavily, and droplets and aerosols from their mouth or nose are launched into the air. At this stage of the pandemic many of the more intrusive restrictions have been lifted, but the virus and the harms that it causes have not gone away. We still continue to see hospital admissions and deaths as a result of COVID and the impacts of long COVID can be significant. That is why it remains important to maximise the use of the remaining measures such as face coverings.
Performers can of course temporarily remove their face covering in some limited indoor situations if other steps are taken. For example, when they are performing or rehearsing they can remove their face covering if they are separated from others by a distance of at least one metre or by a screen or partition.