- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government what the current timelines are for (a) delivering the vessel concept design and (b) the award of the first vessel construction contract in the Small Vessel Replacement Programme.
Answer
The concept design for the Small Vessel Replacement Programme is set to be completed by the end of 2022 with the Single Procurement Document (Scotland) set to issue at the same time.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the answer to question S6W-08743 by Jenny Gilruth on 14 June 2022, whether it will provide the information requested regarding when it will replace the 25 Class 43 HSTs in the ScotRail fleet; whether it will confirm whether Transport Scotland's position remains that such replacement will occur only when "Network Rail has completed the electrification of all or most of the routes they serve", as reported in The Herald on 21 May 2022; when it anticipates that "the electrification of all or most of the routes they serve" will be completed, and for what reason it did not provide this information in its answer.
Answer
The replacement of train fleets in Scotland, including the HSTs, is aligned with the phases of the Decarbonisation Action Plan, a link to which is provided here:- Rail Services Decarbonisation Action Plan | Transport Scotland
This timescale is of course subject to continuous review in line with delivering the decarbonisation of the rail network in Scotland affordably and practicably and any other relevant developments, including recommendations arising from the Steering Groups considering the recommendations of, and subsequent analysis from the recent RAIB report into the Carmont accident.
- Asked by: Finlay Carson, MSP for Galloway and West Dumfries, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 30 June 2022
-
Current Status:
Answered by Humza Yousaf on 25 July 2022
To ask the Scottish Government whether there are current SIGN guidelines for myeloma.
Answer
There are no current SIGN guidelines for myeloma.
The Scottish Intercollegiate Guidelines Network’s (SIGN) list of current guidelines, guidelines under development and archived guidelines that have been, or are being developed or updated by SIGN is available at www.sign.ac.uk.
Where there is no SIGN guideline in place, NHS Boards and Integration Authorities may choose to consider other relevant guidelines such as the National Institute for Health and Care Excellence (NICE) guidelines in the planning and delivery of services.
- Asked by: Monica Lennon, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 30 June 2022
-
Current Status:
Answered by Humza Yousaf on 25 July 2022
To ask the Scottish Government what plans it has to ease the current workload of epilepsy specialist nurses.
Answer
I refer the member to the answer to question S6W-09419 on 13 July 2022. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers .
- Asked by: Stephen Kerr, MSP for Central Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Angus Robertson on 25 July 2022
To ask the Scottish Government what the predicted cost of the Census Coverage Survey 2022 is, and what steps are being taken to ensure its success.
Answer
As the Census Coverage Survey (CCS) is ongoing, the predicted costs are based on the budget assigned to the CCS. Across the lifecycle of the Census Programme it was estimated that a budget of £3.1m would be required to deliver the CCS.
The CCS, alongside high quality administrative data and innovative statistical methods, will build on the census returns to deliver high quality Census Outputs. National Records of Scotland is continuing to take the action necessary to deliver the CCS phase of Scotland's Census Programme.
- Asked by: Richard Leonard, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government whether the maximum performance fee for the Serco Caledonian Sleeper Temporary Measures Agreement is capped at 1.5% of the cost base of the franchise, as was the case for its previous Emergency Measures Agreement, and, if that is not the case, what level it is capped at.
Answer
For the current Serco Caledonian Sleepers Ltd Temporary Measures Agreement in place, there is a small, capped, incentive payment linked to performance and not linked to cost base.
As the performance payments relate to potential future revenues receivable by Serco Caledonian Sleepers Limited, this information currently remains commercially sensitive.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the Infrastructure Investment Plan 2021-22 to 2025-26: Programme pipeline update (March 2022), what assessment it has made of the number of full-time equivalent (a) manufacturing, (b) seafarer and (b) port jobs that could be created in Scotland from the (i) CMAL Net Vessel Investment and (ii) Piers and Harbours Grants programmes.
Answer
The assessments undertaken to inform ferries investments focus on direct infrastructure impacts such as route capacity and connectivity. The benefit realisation process for each project will seek to identify and maximise the positive impact of our investments. As an example of this, the recent introduction of the MV Loch Frisa was enabled by modifications works, instructed by Caledonian Maritime Assets Ltd (CMAL), undertaken at the Dales facility in Leith, and CalMac Ferries Ltd have now completed the recruitment of 38 crew for the vessel to provide the year round commutable service for Mull.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the Infrastructure Investment Plan 2021-22 to 2025-26: Programme pipeline update (March 2022), whether it will provide an update on what commercial discussions Transport Scotland has had with Peel Ports regarding infrastructure work at Ardrossan Harbour.
Answer
Transport Scotland continues to engage with Peel Ports on the commercial arrangements for the Ardrossan upgrade project. The project moved to the tender preparation stage in April 2022 and it will take a number of months to complete prior to progressing to contract award and contractor mobilisation, subject to funding approval and agreeing commercial terms with Peel Ports.
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Monday, 27 June 2022
-
Current Status:
Answered by Jenny Gilruth on 25 July 2022
To ask the Scottish Government, further to the Infrastructure Investment Plan 2021-22 to 2025-26: Programme pipeline update (March 2022), which was published on 15 June 2022, whether it will provide a breakdown of the increase in the cost of tenders for contracts in the Skye Triangle Infrastructure Programme, and what proportion of the budget for that programme has been spent to date.
Answer
The Skye Triangle Infrastructure Programme is estimated to cost around £108million in total for the three port projects: Tarbert (Harris) £23million, Lochmaddy (North Uist) £21million and Uig (Skye) £64million as budgeted following completion of the tender processes. This compares with a total budget of £95million at the time of publishing the Infrastructure Investment Plan in February 2021. The works are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports.
Each of the projects are currently in the construction phase and we estimate total project spend to date to be in the region of £34million. It is the responsibility of the statutory harbour authorities undertaking the works to monitor costs and spend for each of the port projects namely; Caledonian Maritime Assets Ltd (CMAL) for Tarbert, Comhairle nan Eiliean Siar (CNES) for Lochmaddy, and The Highland Council (THC) for Uig.
- Asked by: Monica Lennon, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 23 June 2022
-
Current Status:
Answered by Shirley-Anne Somerville on 25 July 2022
To ask the Scottish Government when it plans to review the policy regarding home educated pupils and entitlement to free school meals.
Answer
There are no plans to review home educated pupils' entitlement to free school meals at present. Free school meals are not normally provided for children and young people whose parents have chosen to home educate them, as the local authority is not responsible for providing their education. Free school meals would only be provided to children and young people who are not receiving their education at a local authority run school if they had entered into an agreement to do so through their local authority. The Scottish Government is not normally made aware of these arrangements.
Local authorities have the flexibility to make discretionary offers of free school meals to families experiencing financial hardship due to exceptional circumstances if they do not meet the regular eligibility criteria. We would urge any families who are home educating their children and experiencing financial hardship to contact their local authority to enquire about what alternative forms of assistance might be available to them.
Families can also access Money Talk Team, a free service provided by Citizen’s Advice on behalf of the Scottish Government that helps to ensure that families are receiving all available benefits and are not paying more than is required for services. More information about this service can be found online at https://moneytalkteam.org.uk/ or by calling their free phone helpline on 0800 085 7145.