- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Tuesday, 24 January 2023
-
Current Status:
Answered by Shona Robison on 7 February 2023
To ask the Scottish Government what progress has been made in relation to the Building Safety Register.
Answer
The Scottish Government has committed to introduce a Register of Buildings by the end of this Parliament. The Register of Buildings will hold information on buildings that have been assessed though the Cladding Remediation Programme. Single Building Assessment reports and remediation activity will define the information that needs to be held in the Register. As this work progresses we are developing the information base for the Register.
- Asked by: Ross Greer, MSP for West Scotland, Scottish Green Party
-
Date lodged: Tuesday, 24 January 2023
-
Current Status:
Answered by Shirley-Anne Somerville on 7 February 2023
To ask the Scottish Government whether it will provide the annual operating cost of the Scottish Survey of Literacy and Numeracy in each of the final three years in which it ran.
Answer
The Scottish Survey of Literacy and Numeracy (SSLN) was an annual sample survey which monitored national performance of school children at P4, P7 and S2 in literacy and numeracy in alternate years. Operating costs are set out in the following table and are broken down by element of spend. As Support Assessors were funded to facilitate group discussions between pupils as part of the Listening and Talking assessment, these costs are only associated with the years that the literacy survey took place.
| £000s | £000s | £000s |
| 2014 (Literacy survey) | 2015 (Numeracy survey) | 2016 (Literacy survey) |
SQA grant funding | 615 | 774 | 682 |
Support Assessors | 117 | - | 117 |
SG analytical staff costs | 175 | 210 | 210 |
Cost of compliance | 398 | 460 | 394 |
Total | 1,305 | 1,444 | 1,403 |
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Tuesday, 24 January 2023
-
Current Status:
Answered by Shona Robison on 7 February 2023
To ask the Scottish Government, further to the answer to question S6O-01324 by Shona Robison on 7 September 2022, what evidence it used to substantiate the statement that “we expect the vast majority of buildings that will be assessed to be found to be safe” prior to any form of building assessment for combustible cladding materials.
Answer
Buildings within the scope of the Cladding Remediation Programme will be subject to a process of increasing assessment scrutiny.
A baseline assessment will identify those buildings which require a full assessment based on an evaluation of fire risk.
The proportion of buildings identified as requiring a full assessment is likely to be low when considering the total number of eligible buildings. This assessment is in line with a House of Commons analysis of the scale of the problems in England.
Single Building Assessments are demand-led and are free for all buildings with residential flatted properties regardless of tenure.
- Asked by: Alexander Burnett, MSP for Aberdeenshire West, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 24 January 2023
Submitting member has a registered interest.
-
Current Status:
Answered by Lorna Slater on 7 February 2023
To ask the Scottish Government whether it will commission NatureScot to lead on red squirrel conservation and embed grey squirrel control in its operations to ensure a future for the red squirrel in Scotland.
Answer
NatureScot has worked with partners on red squirrel conservation, including work to control grey squirrels, for many years. In particular, the Saving Scotland’s Red Squirrel (SSRS) partnership project has been working in strategic areas to protect, maintain and promote existing red squirrel populations since 2007. With support from project staff, professional Grey Squirrel Officers (GSOs) have been working with volunteers and landowners to deliver strategic grey squirrel control.
NatureScot, Scottish Forestry and Forestry and Land Scotland are currently providing core funding for these roles. It remains a priority for the Scottish Government to ensure the important work undertaken by Saving Scotland’s Red Squirrels continues.
- Asked by: Craig Hoy, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 24 January 2023
-
Current Status:
Answered by Humza Yousaf on 7 February 2023
To ask the Scottish Government, in light of the recommendation in the paper, Transforming Nursing, Midwifery and Health Professions’ Roles: Review of Clinical Nurse Specialist and Nurse Practitioner Roles within Scotland, what work it has undertaken to support the development of a generic Level 6 clinical nurse specialist/ specialist nurse practitioner job description, and what impact any such work has had on supporting national consistency.
Answer
I refer the member to the answer to question S6W-14269 on 7 February 2023. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at: https://www.parliament.scot/chamber-and-committees/written-questions-and-answers .
- Asked by: Brian Whittle, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 24 January 2023
-
Current Status:
Answered by Lorna Slater on 7 February 2023
To ask the Scottish Government, further to the answer to question S6W-13230 by Lorna Slater on 20 December 2022, over what period the data used for the modelling by Zero Waste Scotland was collected from local authorities.
Answer
The data used was the last full year of data prior to modelling, wherever possible. This was not always available and, in those circumstances, Zero Waste Scotland agreed with the Local Authority the most appropriate data to be used. The model was then handed over to the Local Authority, allowing updates to be made if more appropriate or recent data became available.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 16 January 2023
-
Current Status:
Answered by Jenny Gilruth on 7 February 2023
To ask the Scottish Government, further to the answer to question S6W-10553 by Jenny Gilruth on 20 September 2022, what the ScotRail budget for Rail Passenger Services (a) is for 2023 and (b) was in each of the years set out in the answer; how much of the budget remained unspent at the end of each of those years, or, if there was an overspend, how much the overspend was, and from which budget line any overspend was funded.
Answer
The draft budget for rail passenger services for (a) 2023-24 is £458 million, as published in December and remains subject to the Parliamentary approval process.
The following table sets out (b) budget against expenditure and explanations for variances that are included in the published outturn statements within the Scottish Government consolidated accounts each year.
Year | Budget £m | Expenditure £m | Comments |
2016-17 | 266 | 266 | No variance |
2017-18 | 311 | 170 | The underspend is offset by an overspend on the capital budget and relates to the reclassification of Fixed Track Access Charges expenditure. |
2018-19 | 183 | 155 | The underspend is offset by an overspend on the capital budget and relates to the reclassification of Fixed Track Access Charges expenditure. |
2019-20 | 150 | 180 | The overspend is due to increased revenue support in response to COVID-19 that was agreed to be funded within the wider SG budget. |
2020-21 | 659 | 659 | No variance |
2021-22 | 568 | 534 | The underspend is due to higher than expected fare box revenue that reduced requirement for COVID-19 support. |
2022-23 | 431 | | Full year not complete. No overspend is expected at this time. |
- Asked by: Jamie Greene, MSP for West Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Dorothy Bain on 7 February 2023
To ask the Scottish Government what its position is on whether any trial of Abu Agila Mohammad Mas'ud Kheir Al-Marimi, in relation to his potential role in the bombing of Pan Am flight 103 over Lockerbie, should take place (a) in a Scottish Court, (b) under Scots Law and (c) inside or outside the United States of America, in light of him having featured on the original Scottish indictment and other similar proceedings having been held under Scots Law in the Netherlands in 2000.
Answer
The Lockerbie bombing remains the worst terrorist atrocity ever committed on UK soil and the effects continue to be felt around the world. The investigation into this terrible atrocity has been conducted jointly by Scottish and American prosecutors and law enforcement for 34 years. 270 people lost their lives that terrible night and 21 countries lost citizens. It has always been an international investigation and I welcome the significant step taken by the United States in obtaining custody of Mr Masoud.
Having been transferred to US custody, Mr Masoud will stand trial in a United States Court, subject to United States laws. That does not diminish the loss suffered by Scotland and many other countries. The 190 American lives lost that night give the United States of America criminal jurisdiction to prosecute Mr Masoud, just as the scene of this terrible crime in Lockerbie and the lives lost here, gave Scotland jurisdiction to prosecute Mr Al-Megrahi and Mr Fhimah under Scots law at Kamp Zeist.
There are no current criminal proceedings in Scotland against Mr Masud. Scottish prosecutors and Police Scotland are dedicated to supporting the US prosecution, just as American counterparts, with assistance from countries around the world, supported the trial at Kamp Zeist to its successful conclusion in 2001.
In December I travelled to Washington DC where I attended a memorial ceremony and met with the US Deputy Attorney General. We discussed how we can continue to work together to obtain justice for all of the victims and their families, and I assured the Deputy Attorney General of Scotland’s unwavering support in this international effort.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
-
Current Status:
Answered by Neil Gray on 7 February 2023
To ask the Scottish Government how many staff are employed by Architecture and Design Scotland, broken down by pay banding.
Answer
The following table sets out the number of Architecture and Design Scotland staff, broken down by pay banding, permanent staff, fixed term appointments (FTA) and full time equivalent (FTE).
Grade | Permanent | FTA | Total | FTE |
A4 | 2 | 0 | 2 | 1.5 |
B1 | 2 | 3 | 5 | 5 |
B2 | 8 | 2 | 10 | 8.5 |
B3 | 12 | 0 | 12 | 11.1 |
C1 | 2 | 0 | 2 | 2 |
SCS | 1 | 0 | 1 | 1 |
Total | 27 | 5 | 32 | 29.1 |
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 27 January 2023
Submitting member has a registered interest.
-
Current Status:
Answered by Lorna Slater on 7 February 2023
To ask the Scottish Government on how many occasions landowners have failed to respond to a formal request made under section 10(2) of the Deer (Scotland) Act 1996 to cull deer.
Answer
There has been one occasion in which the landowner has failed to respond to a formal request under section 10(2) of the Deer (Scotland) Act 1996 to cull deer.
This is in relation to the recent NatureScot intervention in Loch Choire, where the landowner has failed to respond to Section 10(2), resulting in NatureScot staff undertaking culling on the property under Section 10(4) authorisation. NatureScot are currently determining next steps in relation to the use of statutory powers.