- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 23 August 2021
-
Current Status:
Answered by Lorna Slater on 13 September 2021
To ask the Scottish Government how much it has spent on food waste prevention and reduction programmes since 2013.
Answer
Since 2016 - which is when a specific food waste support programme came in - up to April 2021, approx. £1.23 million has been spent.
Table 1 also provides a breakdown of Scottish Government’s advertising spend targeted at food waste prevention and reduction since 2013.
Table 1. Scottish Government food waste advertising spend |
Year | Campaign | Advertising spend |
2013-14 | Eat In Season | £79,903.03 |
2013-14 | Food Waste | £573,102.70 |
2014-15 | Food Provenance | £80,049.11 |
2015-16 | Greener Scotland | £53,042.18 |
2016-17 | Greener Scotland | £103,742.55 |
2017-18 | Greener Scotland | £88,893.75 |
2018-19 | Greener Scotland | £217,737.81 |
2018-19 | Food waste | £303,516.65 |
2019-2020 | Food waste | £53,042.18 |
TOTAL | | £1,553,029.96 |
A breakdown of Zero Waste Scotland’s spend on advertising and outreach activities to promote food waste reduction for 2019-20 and during 2020-21 (to date) and the outcomes of these are set out in Table 2. This forms part of the overall approx. £1.23 million spend mentioned above.
Table 2. Zero Waste Scotland advertising spend and outcomes |
Year | Advertising spend | Outreach spend | Pieces of PR coverage | Increase in social media following | Training delivered on 'Love Food Hate Waste' |
2019-20 | £193,000 | £76,000 | 437 | 17,000 | 1269 individuals |
2020-21 (to date) | £105,000 | £20,000 | 137 | 13,000 | 166 individuals |
TOTAL | £298,000 | £96,000 | | | |
- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 26 August 2021
-
Current Status:
Answered by Lorna Slater on 13 September 2021
To ask the Scottish Government what (a) baseline material input standards have been established for material recovery facilities (MRFs) and (b) improvement in output quality from MRFs has been delivered since 2016.
Answer
This information is publically available through the SEPA Recyclate Quality Reporting Tool, which can be accessed here: https://informatics.sepa.org.uk/RecyclateQuality/
The tool presents data from samples taken from material streams entering and exiting material recovery facilities (MFRs). The tool reports the percentage of materials collected that are considered to be ‘target’ materials for recycling.
- Asked by: Maurice Golden, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 26 August 2021
-
Current Status:
Answered by Lorna Slater on 13 September 2021
To ask the Scottish Government what modelling work it has undertaken on any requirement for residual waste treatment capacity in Scotland, and whether it will provide a breakdown of any forecasts since 2016 for such requirements.
Answer
In April 2019, we published the Waste Markets Study which assessed the treatment options for Scottish biodegradable municipal waste. The study is available here: https://www.gov.scot/publications/waste-markets-study-full-report/
We have also commissioned work to assess the residual waste treatment capacity needs up to 2025, in light of our commitment to end the practice of landfilling biodegradable municipal waste by 2025. This work is ongoing and we will publish it in due course.
- Asked by: Paul Sweeney, MSP for Glasgow, Scottish Labour
-
Date lodged: Monday, 23 August 2021
-
Current Status:
Answered by Kate Forbes on 13 September 2021
To ask the Scottish Government whether it will consider opening a Connecting Scotland phase of applications focused on refugees and asylum seekers, in light of previous phases having centred on certain other vulnerable groups.
Answer
The Scottish Government has committed to extend the Connecting Scotland programme over the course of this Parliament to reach a total of 300,000 people. Work is underway to scope the future service, including how best to reach priority groups who we know are most likely to be digitally excluded, including refugees and asylum seekers.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 02 September 2021
-
Current Status:
Answered by Graeme Dey on 13 September 2021
To ask the Scottish Government, in light of reported delays associated with road surfacing and flooding of the gas network, whether it will provide an update on the delivery timescale for the completion of the A92/A96 Haudagain roundabout improvements.
Answer
The construction of the A92/A96 Haudagain Improvement project is continuing to progress well. It remains that completion is anticipated in winter 2021 as confirmed in the latest Infrastructure Investment Plan update published in June 2021.
This date is subject to any unforeseen circumstances such as the effects of exceptional weather.
- Asked by: Richard Leonard, MSP for Central Scotland, Scottish Labour
-
Submitting member has a registered interest.
-
Date lodged: Thursday, 02 September 2021
-
Current Status:
Answered by Graeme Dey on 13 September 2021
To ask the Scottish Government whether it will provide details of when the contract between Transport Scotland and Jacobs UK Limited, to review transport governance structures in Scotland, was signed, and what the duration of the contract is.
Answer
Jacobs were awarded the review of transport governance structures in Scotland, which formed part of the National Transport Strategy review, through a Task Order. This was progressed as a call off from the previously signed Agreement as a supplier for one of the Lots forming part of the Multi-Supplier Framework Agreement for Transport and Land-Use Modelling and Transport Appraisal and Planning.
The duration of the Task Order was 13 and a half months from November 2017 to 31 December 2018.
- Asked by: Monica Lennon, MSP for Central Scotland, Scottish Labour
-
Date lodged: Monday, 16 August 2021
-
Current Status:
Answered by Michael Matheson on 10 September 2021
To ask the Scottish Government what funding will replace the Climate Challenge Fund, and how it will be delivered in a way that responds to the review of the fund in spring 2019.
Answer
Key to the spring 2019 review was that projects should continue to be designed at a grass roots level but that a more strategic approach to funding was needed to deliver lasting behavioural change.
We are providing a vehicle for communities to come together and engage in collective climate action through the development of a network of regional climate action hubs and climate action towns. These initiatives will empower communities to identify the actions that are most appropriate to their needs.
They will address the findings of the review by developing an integrated network of support that can build capacity for climate action across all communities. They will provide tools and resources to support community-led groups to take action commensurate with our climate commitments and allow for a wide r exchange of knowledge and best practice.
We are also taking steps to better integrate climate objectives into wider SG community initiatives to promote the mainstreaming of climate action, deliver increased value for money and ensure funding delivers on both climate and wider policy outcomes .
- Asked by: Rachael Hamilton, MSP for Ettrick, Roxburgh and Berwickshire, Scottish Conservative and Unionist Party
-
Date lodged: Tuesday, 17 August 2021
-
Current Status:
Answered by Mairi Gougeon on 10 September 2021
To ask the Scottish Government, in light of the findings in the report, Farming for 1.5C: From here to 2045, what approach it plans to take to land-use management, and whether, in future, land-use management will be part of the farm policy agenda.
Answer
The Climate Change Plan update provides a pathway to transform farming and food production in Scotland and to optimise land use. In 2021, we are piloting Regional Land Use Partnerships, which aim to facilitate collaboration between local and national government, communities, land owners, land managers and wider stakeholders. They will enable natural capital-led consideration, at a regional level, of how to maximise the contribution that our land can make to addressing the climate and environment crises.
The proposals set out in the Climate Change Plan update for agriculture are founded on a co-development approach and we will work with the industry to consider the complex issues around multi-faceted land use and decisions that impact on them, while we identify the best way to ensure delivery of these outcomes. This partnership working will be continued through the Agriculture Reform Implementation Oversight Board. The Board will carefully consider the recommendations of the Farmer-led Groups, Farming 1.5, WWF Scotland, Just Transition, NFUS, the Climate Change Plan update and Scotland's Climate Assembly's Recommendations for Action Report when devising practical measures for delivery.
- Asked by: Rachael Hamilton, MSP for Ettrick, Roxburgh and Berwickshire, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 26 August 2021
-
Current Status:
Answered by Mairi Gougeon on 10 September 2021
To ask the Scottish Government whether it will publish details of the selection process for the appointment of Professor Russel Griggs to undertake the external review of the regulatory process involved in fish farming.
Answer
Professor Russel Griggs is already appointed by the Scottish Ministers as the Chair of the Regulatory Review Group which considers regulation, finds ways of improving the regulatory system, advises Ministers on all aspects of Better Regulation and acts as an independent and informed judge of Scottish Government and its regulatory agencies’ Better Regulation performance.
Professor Russel Griggs has been appointed due to his knowledge and previous experience of considering the efficiency and effectiveness of regulatory systems.
- Asked by: Craig Hoy, MSP for South Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 13 August 2021
-
Current Status:
Answered by Graeme Dey on 10 September 2021
To ask the Scottish Government how many times since January 2019 train services between North Berwick and Edinburgh Waverley have been cancelled for (a) all and (b) part of its journey due to (i) track problems, including signalling and flooding, and (ii) track congestion.
Answer
ScotRail advise that between 6 January 2019 [the start of 2018-19: reporting period 11] and 24 July [the end of 2021-22: reporting period 4], there were 216 full cancellations and 74 part-cancellations on the North Berwick line as a result of infrastructure issues.
While full- or part-cancellations as a result of track congestion are not reported separately, ScotRail also advise that there were a further 34 full cancellations and 29 part-cancellations to ScotRail services as a result of the actions of other train operating companies.