- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Kate Forbes on 17 March 2022
To ask the Scottish Government whether it carried out a survey of the (a) MV Glen Sannox and (b) Hull 802 vessels prior to taking Ferguson Marine Engineering Ltd into public ownership, and whether it identified any issues during those surveys, and, if so, what those issues were.
Answer
Prior to the Scottish Government taking control of the yard leading to Nationalisation, it was not possible to undertake a detailed analysis of the work required to complete the vessels. The detailed design and planning was the responsibility of the former owners of the yard.
It was only once the yard was in Scottish Government control that the full information was available and the full extent of issues with the design and approval of the ship become known. On 18 December 2019, the Turnaround Director submitted a report on the conditions of the two ferries, together with a revised programme and cost to complete the vessels. A copy of the report can be found on the Scottish Government website – Ferguson Marine: report on cost and programme for vessels 801 and 802 - gov.scot (www.gov.scot) .
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Maree Todd on 17 March 2022
To ask the Scottish Government, further to the answer to question S6W-06126 by Maree Todd on 28 February 2022, by what date it estimates that all screening centres will have offered women aged 53 to 70 their breast screening appointments within 39 months of their previous screening.
Answer
Modelling work completed prior to omicron suggested it would be March 2023 before all screening centres in Scotland would reach the point of being able to offer breast screening rounds of 39 months. There are however a number of factors at play including the ongoing pandemic, the steps we are continuing to take to increase capacity in the screening programme, as well as options that are being considered to accelerate the recommencement of self-referrals for women over-70.
- Asked by: Alexander Burnett, MSP for Aberdeenshire West, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Kate Forbes on 17 March 2022
To ask the Scottish Government how many vouchers have been received in each local authority area as part of the R100 Scottish Broadband Voucher Scheme.
Answer
Figures for vouchers requested, vouchers issued and installations completed to date through the use of the R100 Scottish Broadband Voucher Scheme are provided in the following table:
| | INTERIM VOUCHER SCHEME | MAIN VOUCHER SCHEME |
Local Authority | Vouchers Requested | Vouchers Issued | Installations Completed | Vouchers Requested | Vouchers Issued | Installations Completed |
Aberdeen City | | | 1 | | 8 | 13 |
Aberdeenshire | 3 | 41 | 75 | 12 | 175 | 271 |
Angus | 4 | 1 | 8 | | 103 | 39 |
Argyll & Bute | | 8 | 13 | | 24 | 37 |
City of Edinburgh | | | | | 14 | 12 |
Clackmannanshire | 1 | 1 | 7 | | 1 | 5 |
Dumfries & Galloway | | 7 | 110 | | 28 | 23 |
Dundee City | | | | | 17 | 1 |
East Ayrshire | | 1 | 16 | | 6 | 7 |
East Dunbartonshire | | | | | 2 | 1 |
East Lothian | | | 3 | | 15 | 7 |
East Renfrewshire | 1 | | 5 | | 4 | 4 |
Falkirk | | 1 | 4 | 2 | 10 | 2 |
Fife | | 1 | 10 | 1 | 16 | 21 |
Glasgow City | | | | | 9 | 9 |
Highland | 1 | 7 | 45 | 1 | 161 | 196 |
Inverclyde | | | 1 | | | 1 |
Midlothian | | | 11 | | 15 | 6 |
Moray | 1 | 5 | 27 | 1 | 75 | 75 |
North Ayrshire | | | 10 | | 1 | 16 |
North Lanarkshire | | 1 | 7 | | 18 | 11 |
Orkney Islands | | | | 5 | 60 | 9 |
Perth & Kinross | 1 | 17 | 78 | 1 | 37 | 45 |
Renfrewshire | | | 7 | | 11 | 4 |
Scottish Borders | 2 | 14 | 154 | | 31 | 57 |
Shetland Islands | | | | | | |
South Ayrshire | | | 2 | | 1 | 11 |
South Lanarkshire | 1 | 3 | 39 | | 6 | 21 |
Stirling | | 5 | 104 | 7 | 17 | 24 |
West Dunbartonshire | | | 2 | | | |
West Lothian | | | 1 | | | 2 |
Western Isles | | | | | | |
Blanks * | | | | | | |
Total | 15 | 113 | 740 | 30 | 865 | 930 |
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Shona Robison on 17 March 2022
To ask the Scottish Government how many full single building assessments (a) have been completed and (b) will be completed by the end of the financial year 2021-22.
Answer
The Programme is actively supporting 25 blocks through key stages of assessment. As this is a representative-led process the time to completion of each Single Building Assessment cannot be accurately predicted.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Maree Todd on 17 March 2022
To ask the Scottish Government, further to the answer to question S6W-06126 by Maree Todd on 28 February 2022, what its position is on whether over-70s breast cancer screening will have restarted by the end of 2022.
Answer
As answered PQ S6W-06126, in recognition of the anxiety the pause is causing, I have asked for work to explore options that will accelerate the restart of self-referrals for women aged 71 and over. Any decision will be informed by clinical advice and the on-going pandemic. As part of these considerations our goal is to restart the option to self-refer by the end of September 2022, with a number of factors still to be worked through. The restart will be done in a phased way without unduly impacting appointment times for the eligible screening population for whom there are clear screening benefits. Every effort continues to be made to increase capacity in the screening programme, including through deploying additional mobile units and offering weekend and evening appointments.
Regardless of their age, women should remain symptom aware and report any symptoms to their GP immediately for these to be investigated.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Kate Forbes on 17 March 2022
To ask the Scottish Government whether Ferguson Marine (Port Glasgow) Ltd identified any issues with the cabling for MV Glen Sannox prior to the week ending 24 December 2021.
Answer
The Turnaround Director wrote to the Net Zero, Energy and Transport Committee on 9 February 2022, confirming that the cabling issue emerged in the week ending 24 December 2021. This remains the yards current understanding.
- Asked by: Donald Cameron, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Kate Forbes on 17 March 2022
To ask the Scottish Government, in light of the Ferguson Marine confirmation that “at least 400 cables will need to be addressed with the worst case 939 cables” on MV Glen Sannox, how much it estimates each scenario will cost to remedy.
Answer
The CEO of Ferguson Marine is preparing an update, for the Net Zero, Energy and Transport Committee, on the delivery timetable and budget for vessels 801 and 802 which will be submitted before the end of March 2022.
- Asked by: Dean Lockhart, MSP for Mid Scotland and Fife, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Kate Forbes on 17 March 2022
To ask the Scottish Government when it first became aware of potential issues with the dual-fuel engines ordered from the Finnish company, Wärtsilä, for the delivery of two ferries for the CalMac fleet.
Answer
The Scottish Government are aware the warranty on the engines for vessels 801 & 802 has lapsed. Discussions with CMAL and Ferguson Marine are ongoing on how to accommodate this.
- Asked by: Mark Ruskell, MSP for Mid Scotland and Fife, Scottish Green Party
-
Date lodged: Friday, 04 March 2022
-
Current Status:
Answered by Lorna Slater on 17 March 2022
To ask the Scottish Government whether there is a 70% recycling target for household waste, as set out in annex A, section 5.5, of Scotland's Zero Waste Plan.
Answer
The Zero Waste Plan sets out the 70% of all waste recycled target in the main section of the document. The suggestion of a 70% household specific waste recycling target in Annex A, section 5.5, is incorrect.
Scotland’s target to recycle 70% of all waste by 2025 is a key commitment, underlined in our ‘ Making Things Last ’ Circular Economy Strategy and Climate Change Plan update .
- Asked by: Katy Clark, MSP for West Scotland, Scottish Labour
-
Date lodged: Tuesday, 22 February 2022
-
Current Status:
Answered by Jenny Gilruth on 17 March 2022
To ask the Scottish Government on which date it expects to have concluded the (a) Community Needs and (b) Market Assessment on all routes in the contract for the Clyde and Hebrides Ferry Service, and whether Transport Scotland has tendered any contracts for this work.
Answer
These assessments will be undertaken as part of work on the Scottish Government's Islands Connectivity Plan (ICP). Community needs assessments establish the level of transport connectivity required by each island and remote mainland community within scope of ICP and will update assessments undertaken for the Ferries Plan 2013-2022. Market assessments consider whether the required level of transport connectivity can be provided without government intervention.
The exact timescales for these assessments is still to be determined. We aim to make significant progress with these assessments during 2022 and conclude any outstanding work during 2023. Priority is currently being given to assessments required to support the business cases for live vessel and port investment projects.
Transport Scotland has not yet invited tenders for work on any of these assessments. It is expected that the work will be undertaken utilising both internal staff resource and external consultancy.