- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 01 March 2023
-
Current Status:
Taken in the Chamber on 9 March 2023
To ask the Scottish Government how it engages with local communities to ensure that their transport needs are met.
Answer
Taken in the Chamber on 9 March 2023
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government, before an order was placed for Hull 802, whether an alternative option of ordering two smaller vessels to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes was considered, and, if it was the case, for what reason any such alternative option was rejected, and, if it was not the case, for what reason such an alternative option was not considered.
Answer
The proposal for the procurement of what became vessels 801 and 802 was set out in the Vessel Replacement and Deployment Plan (VRDP) Annual Report 2014 vrdp-annual-report-2014.pdf (transport.gov.scot)
The recently published Ferries Plan 2013-2022 had concluded that the level of services then in place on the Uig-Tarbert/Lochmaddy routes met identified community needs. Vessel 802 was earmarked for initial deployment to those services, to bring additional vehicle deck capacity; noting that the deployment plan would be reviewed prior to delivery.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government what the current estimated total cost, including design, contract management, construction, legal, and administrative costs, is for the upgrading of the ferry terminal at Lochmaddy to allow its use by Hull 802, and what percentage of the total cost will be funded by (a) it and (b) other bodies.
Answer
The works at each of the ports as part of the Skye Triangle Infrastructure programme (Tarbert, Lochmaddy & Uig) are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports. The Lochmaddy project is estimated to cost £21million. Our response to the Freedom of Information Request 2022-00297832 published in July 2022 outlined that we have offered a capital funding contribution of up to £15,747million with the remaining contribution to be met by the Comhairle nan Eilean Siar (CNES) as statutory harbour authority.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government what the current estimated total cost, including design, contract management, construction, legal, and administrative costs, is for the upgrading of the ferry terminal at Tarbert to allow its use by Hull 802, and what percentage of the total cost will be funded by (a) it and (b) other bodies.
Answer
The works at each of the ports as part of the Skye Triangle Infrastructure programme (Tarbert, Lochmaddy & Uig) are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports. The Tarbert (Harris) project is estimated to cost £23million. Our response to the Freedom of Information Request 2022-00297832 published in July 2022 outlined that we have offered a capital funding contribution of up to £19.599million with the remaining contribution to be met by Caledonian Maritime Assets Ltd (CMAL) as statutory harbour authority.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 28 February 2023
To ask the Scottish Government what the current estimated total cost, including design, contract management, construction, legal, and administrative costs, is for the upgrading of the ferry terminal at Uig to allow its use by Hull 802, and what percentage of the total cost will be funded by (a) it and (b) other bodies.
Answer
The works at each of the ports as part of the Skye Triangle Infrastructure Programme (Tarbert, Lochmaddy & Uig) are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports. The Uig project is estimated to cost £64million. Our response to the Freedom of Information request: 2022/00297832 published in July 2022 outlined that we have offered a capital funding contribution of up to £38million with the remaining contribution to be met by the Highland Council as statutory harbour authority.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government when it last received an update from CMAL on the progress of the two ferries that it has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
Answer
The Scottish Government receives regular updates on all new vessel builds. The contract for the Little Minch vessels was signed on 11 January and all agreements including full Builders Refund Guarentees were put in place recently. The latest update was received from CMAL on 20 February 2023.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government what the total cost will be of the two vessels that CMAL has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
Answer
The Scottish Government announced up to £115 million funding for the two Little Minch vessels, and associated port works and project costs, in October 2022. The total costs of the vessels are commercially confidential.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government whether the two vessels which CMAL has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes could have operated from ferry terminals at (a) Uig, (b) Lochmaddy and (c) Tarbert without the reconstruction and dredging operations being carried out at each terminal to allow their use by Hull 802.
Answer
The vessels currently under construction at Cemre could not have served the ports at Uig, Lochmaddy and Tarbert without changes to infrastructure. The works at each of the ports are aimed at replacing life expired infrastructure, improving resilience and increasing the range of vessels that can use the ports.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 27 February 2023
To ask the Scottish Government whether there have been any design changes to the two vessels that CMAL has ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
Answer
CMAL as procuring authority have confirmed that there have been no changes to the design or specifications for the vessels ordered from the Cemre Marin Endustri yard to serve on the Uig to Lochmaddy and Uig to Tarbert ferry routes.
- Asked by: Jamie Halcro Johnston, MSP for Highlands and Islands, Scottish Conservative and Unionist Party
-
Date lodged: Monday, 30 January 2023
-
Current Status:
Answered by Jenny Gilruth on 21 February 2023
To ask the Scottish Government what the (a) length, (b) beam and (c) maximum operational draught of MV Hebrides is.
Answer
MV Hebrides is 99 metres in length, 15.8 metres wide and her operational draught, which is the vertical distance between the waterline and the bottom of the vessel’s hull, is 3.3 metres.
Further information is available on CalMac’s website by following the link: https://www.calmac.co.uk/fleet/mv-hebrides