- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Jenny Gilruth on 26 September 2022
To ask the Scottish Government when it plans to publish its 10-year islands connectivity plan, and what assessment it has made of any impact of not having done so on people in remote and island communities, particularly in relation to the adequacy of ferry services.
Answer
I refer the member to the answer to question S6W-09901 on 15 August 2022. All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers
There is an existing Ferries Plan in place until December 2022.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 08 September 2022
-
Current Status:
Answered by Mairi McAllan on 26 September 2022
To ask the Scottish Government whether it will provide an update on its response to the Environment, Climate Change and Land Reform Committee’s December 2020 report on regional marine planning, following Marine Scotland’s internal review.
Answer
We continue to carefully consider the report and recommendations made by the previous Environment, Climate Change and Land Reform Committee as regards regional marine planning and are working to finalise our formal response, which will be published this Autumn.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 26 August 2022
-
Current Status:
Answered by Michael Matheson on 23 September 2022
To ask the Scottish Government, further to the answer to question S6W-10006 by Michael Matheson on 23 August 2022, in light of it stating that it has not yet assessed the cost of achieving net zero greenhouse gas emissions by 2045 and not providing a suggestion of a figure, whether it has at least assessed the cost of achieving net zero greenhouse gas emissions by 2045 within an approximate range or figure, or whether it has no estimate of the cost of achieving net zero greenhouse gas emissions by 2045.
Answer
The costs of global failure to address the climate emergency would be enormous and the Scottish Government is committed to leading the way in delivering early action to reduce emissions while at the same time positioning Scotland to secure and share the opportunities from the transition. The next Climate Change Plan, a draft of which will be published next year, will include costs of delivering emissions reductions to meet the statutory targets between 2025 and 2040. The Scottish Government has not set out a pathway to net zero greenhouse gas emissions by 2045 and hence does not yet have a basis for a cost assessment of achieving that goal. The Climate Change Committee suggest “the net costs of the transition (including upfront investment, ongoing running costs and costs of financing) will be less than 1% of GDP over the entirety of 2020-2050”. We believe this is a reasonable estimate while noting that the cost totals and profile for Scotland may differ due to our stricter statutory targets and the likelihood that our pathway to net zero may diverge from that taken by the UK as a whole.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 24 August 2022
-
Current Status:
Answered by Michael Matheson on 21 September 2022
To ask the Scottish Government what the combined generating capacity in GW will be of the projects that it anticipates will be constructed under the ScotWind leasing round; whether it remains of the view, set out in its 2020 Sectoral Marine Plan for Offshore Wind Energy, that "...an overall national limit on generating capacity of 10GW was required as a mitigation measure”, and what the total actual investments in the Scottish supply chain will be, in light of the Cabinet Secretary for Net Zero, Energy and Transport's reported statement in January 2022 that ScotWind "will secure investment in the Scottish supply chain of at least £1 billion for every GW of power".
Answer
Following the clearing announcement on the 22 August 2022, the ScotWindleasing round has identified 20 offshore wind projects with a potential overall capacity of 27.6GW. Based on the Supply Chain Development Statements (SCDS) submitted with the leasing applications, developers have committed to invest around £1.4bn per project.
Before construction, these projects will go through project development and consenting processes, respond to geographical and technological requirements, and find a route to market. For this reason, it is not possible to have a clear indication at this time of what will be constructed and the combined generating capacity.
The Sectoral Marine Plan for Offshore Wind Energy (SMP-OWE) assessed a potential generation figure of 10GW and therefore does not comment on additional generation or impacts. The SMP-OWEis subject to an Iterative Plan Review (IPR) process, which allows Scottish Government to review the conclusions of the Plan against new available information. Through the IPR process we will consider the impacts of the new potential generation figure of 27.6GW.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 07 September 2022
-
Current Status:
Answered by Patrick Harvie on 21 September 2022
To ask the Scottish Government what its assessment is of the comparable costs of running an air source heat pump in a non-retrofitted, non-fabric refitted average property, compared with a gas boiler.
Answer
Scotland has a varied building stock, with many different ages and types of properties. Homes are built with various levels of insulation, with many having altered the building fabric since construction (for example by installing double glazing). This makes defining a ‘non-retrofitted home’ challenging. The most consistent approach to comparing the running cost of a heat pump to the running cost of a gas boiler is to compare the relative cost of heat from each system, taking into account their differing efficiencies.
Under the recently announced Energy Price Guarantee, the unit rate of gas for the average consumer is 10.3 p/kWh, compared to 34.0 p/kWh for electricity. While estimates of the energy efficiency of heat pumps vary, air source heat pumps are typically considered to be two to three times more efficient than gas boilers. Therefore, we estimate broadly that a home with the average heat demand would face an estimated annual cost of around £1,900 using a gas boiler, compared to around £2,000 using an air source heat pump. This estimate is illustrative and subject to uncertainty. It is based on average household demand for heat and varies in line with assumed levels of gas and electricity prices, as well as the assumed efficiencies of the respective heating systems.
The Heat in Buildings Strategy proposes to set minimum energy efficiency standards alongside heating system change, so that the energy efficiency of our housing stock will be improved ahead of, or in tandem with, a zero direct emissions heating system being installed. This approach will reduce the running cost of zero direct emissions heating systems, such as heat pumps. We therefore don’t expect that heat pumps will be installed in properties unless the energy efficiency is at an appropriate level, which is currently being developed through external research.
Electricity policy and regulation is reserved to the UK Government. The Scottish Government is calling on the UK Government to take urgent action to rebalance gas and electricity prices such that the running costs of zero direct emission heating systems are more favourable compared with fossil fuel incumbents.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 24 August 2022
-
Current Status:
Answered by Jenny Gilruth on 20 September 2022
To ask the Scottish Government what the total final cost of ScotRail's nationalisation was, in relation to the transfer of operations of ScotRail from Abellio to the nationalised operator.
Answer
The decision to bring ScotRail under public control avoided the need to run an expensive and inappropriate rail franchising competition. Though widely acknowledged as a failed model, franchise competitions remain the preferred approach in current UK Legislation. Such exercises typically cost in excess of £10m for franchising authorities, as well as the similarly significant costs of each bidder.
As confirmed during my Net Zero, Energy and Transport Committee appearance on 15 March 2022, prior to that date, since the decision to proceed with the “Operator of Last Resort” (OLR) option was taken in March 2021, £3.6 million had been spent on the OLR activity.
Final reconciliation figures confirm that £5.5 million has been spent in total on OLR activity, and ScotRail Trains Ltd. was mobilised successfully on 1 April. I am confident you will notice the saving this achieved when compared with a franchising competition.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Wednesday, 24 August 2022
-
Current Status:
Answered by Jenny Gilruth on 20 September 2022
To ask the Scottish Government, further to the answer to question S6W-09822 by Jenny Gilruth on 5 August 2022, what the ScotRail budget has been in each year from 1 April 2016 to 1 April 2023, and, for each year, what proportion of the budget, expressed as a percentage, was allocated to (a) staff costs, (b) rolling stock improvements and changes, (c) station facilities, (d) rail replacement services, (e) maintenance, operations and upgrades and (f) any other headline category of spend used by ScotRail.
Answer
The Scottish Government does not hold the details of ScotRail expenditure broken down by the categories you have requested.
The Scottish Government budget for Rail Passenger Services, which covers both ScotRail and Caledonian Sleeper, has been published as :
2016 £266m
2017 £311m
2018 £183m
2019 £150m
2020 £239m
2021 £370m
2022 £407m
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Thursday, 25 August 2022
-
Current Status:
Answered by Keith Brown on 20 September 2022
To ask the Scottish Government how many successful prosecutions for stalking and harassment offences there have been in (a) Scotland and (b) Aberdeen in each year from 2018-19 to 2022-23 to date.
Answer
The latest available information on the number of people convicted for ‘stalking offences’ is provided in the following table.
Number of people proceeded and convicted for stalking offences (where main crime) in Scottish courts, 2018-19 to 2020-21.
| Scotland | Aberdeen |
Total prosecuted | Total Convicted | Total prosecuted | Total Convicted |
2018-19 | 620 | 531 | 57 | 44 |
2019-20 | 562 | 496 | 33 | 25 |
2020-21 | 249 | 219 | 11 | 9 |
Source: Scottish Government Criminal Proceedings database
Please note: Information for 2021-22 will not be available until publication of the Criminal Proceedings in Scotland, 2021-22 Statistical Bulletin. This is due to be published in 2023.
We are unable to provide data on harassment. There is no specific crime of harassment and harassment can conform to a wide range of both criminal offences and civil matters. As such there are no meaningful data we can provide.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 26 August 2022
-
Current Status:
Answered by Richard Lochhead on 20 September 2022
To ask the Scottish Government, further to the answer to question S6W-10025 by Richard Lochhead on 22 August 2022, whether it anticipates the reported approximately 70,000 jobs currently sustained in the north east by oil and gas to remain in the north east by 2030, whether in oil and gas and/or renewables.
Answer
The Robert Gordon University report – Making the Switch, funded through the North-East Economic Recovery and Skills Fund (NEERSF), estimates between 70,000 and 80,000 people are directly and indirectly employed in the offshore energy sector in Scotland, with around 65% working or based in the North East.
This report highlights over 90% of the workforce has medium to high skills transferability between adjacent energy sectors, such as offshore wind, the use of hydrogen and carbon capture and storage. This indicates the North East is well placed to capitalise on the opportunities associated with the energy transition and could become either a UK or Global Energy Hub, with the expected result of the energy workforce remaining broadly stable or increasing by 2030.
The Scottish Government is supporting this transition from the oil and gas sector to renewables and low carbon through a number of programmes, including, but not limited to, the £75 million Energy Transition Fund and our £500 million Just Transition Fund for the North East and Moray.
The Climate Emergency Skills Action Plan is key to ensuring everyone can benefit from the opportunities a Just Transition can create, whether the requirement is to improve on existing skills or retrain to a new or emerging green job.
- Asked by: Liam Kerr, MSP for North East Scotland, Scottish Conservative and Unionist Party
-
Date lodged: Friday, 26 August 2022
-
Current Status:
Answered by Richard Lochhead on 20 September 2022
To ask the Scottish Government how many applications have been received to the Just Transition Fund to date; whether it will provide the full list of locations for advertising the fund; when the application process for the first £20 million closes, and when the first £20 million will be awarded to successful applicants.
Answer
The application window for the first year of the Just Transition Fund closed on 15 July 2022, with a total of 102 proposals received.
The Fund was advertised through the Scottish Government’s website and social media platforms, as well as through local partners, including: Aberdeenshire Council, Moray Council; Aberdeen City Council; Aberdeen and Grampian Chamber of Commerce; Moray Chamber of Commerce; and the Just Transition Partnership. The Fund was also advertised through the ‘Find Business Support’ portal.
Applicants were notified about the outcome of their proposals on 6 September 2022, but the full list of projects won’t be published until after the mourning period following the passing of Her Majesty The Queen.