- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 19 August 2022
To ask the Scottish Government, further to the answer to question S6W-08297 by Shona Robison on 12 May 2022, whether it will
provide an update on how many properties are at each stage of assessment, how
many single building assessments have been supplied to building owners, and
what the average amount of time is that each phase has taken.
Answer
Single Building Assessment applicants are supported through the process to complete the application form and commission professional services ahead of receiving the final survey report. 10 pilot blocks are within the Application Phase and 15 pilot blocks are within the Delivery Phase. The Single Building Assessment provides an individualised process therefore timescales vary on a building by building basis.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 19 August 2022
To ask the Scottish Government, further to the answer to question S6W-09252 by Shona Robison on 21 July 2022, whether these sums of money are included in the Single Building Assessment programme: spending information, which was released on 12 May 2022, and how much has been spent on contractors (a) prior to July 2021 and (b) in July and August 2022.
Answer
Contractor spend prior to July 2021 was £0. b) The contractor spend for July 2022 is £16,422 and August 2022 projected spend is £18,829.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Wednesday, 03 August 2022
-
Current Status:
Answered by Shona Robison on 19 August 2022
To ask the Scottish Government, whether it will prepare a medium-rise inventory, in light of the Building (Scotland) Amendment Regulations 2022, which ban combustible cladding on buildings with any storey at a height of more than 11 metres above the ground.
Answer
As part of the Cladding Remediation Programme we will create a Building Safety Register. This register will include blocks of flats, of any height, assessed as 'low risk' or remediated as an outcome of the Single Building Assessment process.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 04 August 2022
-
Current Status:
Answered by Shona Robison on 16 August 2022
To ask the Scottish Government for what reason the draft Bill regarding tenement maintenance will not be introduced until 2026, and whether it will ask the Scottish Law Commission to review its timetable.
Answer
I refer the member to my response on this matter, which was sent to the Delegated Powers and Law Reform Committee on 25 March 2022, and which is published in the correspondence of that Committee on the Scottish Parliament website at response-from-shona-robison-25-march.pdf (parliament.scot) .
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Tuesday, 05 July 2022
-
Current Status:
Answered by Shona Robison on 4 August 2022
To ask the Scottish Government (a) how many times and (b) on what dates it has met with stakeholders that are concerned with cladding remediation, including (i) insurers, (ii) mortgage lenders, (iii) the Scottish Fire and Rescue Service and (iv) homeowners, regarding the cladding remediation programme, since the Single Building Assessment pilot began.
Answer
Since the start of the pilot in June 2021 Scottish Government has met individually with:
Association of British Insurers 5 times
- on 13 August 2021, 19 August 2021, 6 October 2021, 11 November 2021,
3 March 2022,
UK Finance 6 times
- on 13 July 2021, 18 August 2021, 19 August 2021, 22 February 2022, 6 April 2022, 21 April 2022
SFRS 2 times
- on 9 July 2021, 15 September 2021
High Rise Scotland Action Group
- 15 times on 30 July 2021, 13 August 2021, 16 August 2021, 19 August 2021, 2 December 2021, 10 December 2021, 17 January 2022, 11 February 2022, 18 February 2022, 4 March 2022, 25 April 2022, 26 April 2022, 9 May 2022, 11 May 2022, 6 July 2022.
Pilot building homeowners association representatives
The Scottish Government has met with all stakeholders collectively at meetings of the Cladding Stakeholder Group. It has met on these dates:
2021
- 30 June, 19 August, 15 September, 20 October, 17 November, 15 December.
2022
19 January, 16 February, 16 March, 20 April, 18 May.
Officials have also met with the SFRS regularly, at times daily, and likewise for homeowners affected by the cladding crisis. It is impossible to attach a figure to these meetings.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Tuesday, 05 July 2022
-
Current Status:
Answered by Shona Robison on 4 August 2022
To ask the Scottish Government how many times it has met with Homes for Scotland regarding the development of the Scottish Safer Buildings Accord; what progress has been made with the Accord, and whether it will publish minutes and papers relating to the development of the Accord.
Answer
The Scottish Government has met 8 times with Homes for Scotland directly related to the development of the Scottish Safer Buildings Accord workshops.
We are making significant progress, to date focused around collaborative service design of the high level principles and scope. We are working at pace with our design cohort to refine specific technical criteria and build up granularity to the Accord.
Officials, in keeping with good collaborative working and Service Design, continue to meet regularly with Homes for Scotland out with design workshops and it is impracticable to attach a figure to these.
Discussions are sensitive and of a commercial, financial and legal nature. These will understandably not be published due to the confidential nature of discussions.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Tuesday, 05 July 2022
-
Current Status:
Answered by Patrick Harvie on 27 July 2022
To ask the Scottish Government how many community-run retrofit organisations does it fund.
Answer
Scottish Government funding schemes, in the main, do not fund community-run retrofit organisations directly.
However, a number of our schemes do support retrofitting. For example, our flagship Community and Renewable Energy Scheme (CARES), delivered by Local Energy Scotland, has offered advice to over 900 organisations and supported over 600 community and locally owned renewable projects throughout Scotland, offering funding of over £58 million since its inception in 2010. CARES has supported 119 organisations to retrofit decarbonised heat and/or install renewable generation into their buildings.
The following schemes also provide support to households, businesses and other eligible organisations for retrofitting, though not exclusively:
- Warmer Homes Scotland – more than £176 million has been invested through the scheme since its launch in September 2015 helping over 27,000 households throughout Scotland.
- Area Based Schemes – up until the end of the 2020-2021 programme, £400 million has been invested delivering 110,000 measures to homes since 2013.
- Home Energy Scotland loans and cashback – since 2017, the scheme has issued 6808 loans, valued at over £37 million, and 4097 cashback offers, valued at over £11 million, to existing homes.
- SME loans and cashback – since 2008, the scheme has paid close to £40 million in loans and cashback, funding more than 1627 projects.
- Social Housing Net Zero Heat Fund – since August 2020, the fund has committed over £14 million to the retrofit of 1800 social homes across Scotland.
- Low Carbon Infrastructure Transition Programme – this programme has provided grant support for the retrofitting of over 1000 homes to decarbonise their energy consumption.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 01 July 2022
Submitting member has a registered interest.
-
Current Status:
Answered by Shona Robison on 21 July 2022
To ask the Scottish Government what the (a) budget and (b) outturn has been for the First-tier Tribunal for Scotland (Housing and Property Chamber) in each year since 2016.
Answer
The Scottish Government budget and outturn for the First-tier Tribunal for Scotland (Housing and Property Chamber) in each year since 2016 is in the following table:
| SG Budget First-tier Tribunal for Scotland (Housing and Property Chamber) | Budget Outturn |
2016-17 | Information not held | 995,376 |
2017-18 | 1,796,000 | 1762411 |
2018-19 | 4,333,000 | 3,147,000 |
2019-20 | 3,494,000 | 4,219,000 |
2020-21 | 3,494,000 | 3,694,000 |
2021-22 | 3,494,000 | 3,848,000 |
These figures are for the Scottish Government budget which part funds the costs of the First Tier Tribunal Housing and Property Chamber.
The First Tier Tribunal is an independent judicial body. As such, information on operational costs are held by the Scottish Court and Tribunals Service (SCTS) corporate body.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 23 June 2022
-
Current Status:
Answered by Shona Robison on 21 July 2022
To ask the Scottish Government what the average day rate is of the contractors in its Cladding Remediation Unit.
Answer
For the year 2022 to date the average day rate is £505.03 (inclusive of VAT).
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Thursday, 23 June 2022
-
Current Status:
Answered by Shona Robison on 21 July 2022
To ask the Scottish Government (a) how many contractors have worked and (b) what the expenditure has been on contractors, in its Cladding Remediation Unit in each of the last 12 months.
Answer
(a) there have been a total of 4 contract workers in the past 12 months.
(b) see the following table
Month | Date | Costs (inc VAT) | Number of Contractors |
1 | Jul-21 | £ 6,659.39 | 1 |
2 | Aug-21 | £ 4,324.85 | 1 |
3 | Sep-21 | £ 8,710.49 | 1 |
4 | Oct-21 | £ 1,028.20 | 1 |
5 | Nov-21 | £ - | 0 |
6 | Dec-21 | £ - | 0 |
7 | Jan-22 | £ - | 0 |
8 | Feb-22 | £ - | 0 |
9 | Mar-22 | £ - | 0 |
10 | Apr-22 | £ 16,098.00 | 3 |
11 | May-22 | £ 33,333.96 | 3 |
12 | Jun-22 | £ 23,365.20 | 3 |
| Total | £ 93,520.09 | |