- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Wednesday, 10 August 2022
Submitting member has a registered interest.
-
Current Status:
Answered by Shona Robison on 7 September 2022
To ask the Scottish Government how many staff have been (a) trained and (b) allocated to deal with applications for the Home
Owners' Support Fund, in each of the last six years.
Answer
The following table shows how many staff have been allocated to the Home Owners Support Fund in recent years. Staff are fully trained and highly experienced and levels have been sufficient to meet demand for the Fund.
Financial Year | Number of HOSF Staff |
2015-16 | * |
2016-17 | 6 |
2017-18 | 5 |
2018-19 | 3 |
2019-20 | 3 |
2021-22 to present day | 4 |
* No figure for this year
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Wednesday, 10 August 2022
Submitting member has a registered interest.
-
Current Status:
Answered by Shona Robison on 7 September 2022
To ask the Scottish Government, further to the answer to question S6W-08749 by Shona Robison on 14 June 2022, and in light of the Bank of England increasing the base rate to 1.75%, when the review
(a) began and (b) will complete, and how it will announce the findings and
outcomes of the review.
Answer
An internal review of the Home Owners Support Fund began in the Spring and will complete later this year. If Ministers decide to make any changes to the eligibility or operational arrangements for the scheme updated guidance will be published.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09248 by Shona Robison on 20 July 2022, what pre-contracting activity it has undertaken to establish (a) how many contractors will be required to deliver assessments for all 29 buildings, (b) the (i) availability and (ii) capacity of surveyors and fire engineers to carry out the contract, and, in the event that any such pre-contracting assessments have identified an insufficient supply of contractors, what it anticipates the likely training needs will be to meet any identified requirements.
Answer
Every building must gain the consent of homeowners in order to begin the contract process. Every building will require a qualified Fire Assessor to spend typically a number of weeks on and off-site to gather sufficient data and evidence to conduct a competent Single Building Assessment.
We are aware of the supply chain constraints in this field which is why we are working closely with Royal Institution of Chartered Surveyors and the Institute of Fire Engineers to ensure an appropriate stream of qualified assessors.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government how the single building assessment is designed to take account of any risk of electric vehicle
fires, whether any specific assessment protocols are included in the assessment
to respond to any such risks and, if this is the case, whether it will provide
the details of any such protocols.
Answer
A Single Building Assessment will deliver a full assessment of fire risks on a building by building basis to highlight any issues related to fire safety including, but not limited to underground car parks and charging points.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09248 by Shona Robison on 20 July 2022, whether it will prioritise the assessment of the 29 buildings in the event of a limited supply of surveyors and fire engineer contractors, and if so, what the process will be for carrying out any such prioritisation.
Answer
We are aware there may be constraints in the market place and we are working closely with a number of Scottish firms and with industry bodies and forums to monitor market availability, therefore we are able to prioritise Single Building Assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answers to questions S6W-09248 and S6W-09249 by Shona Robison on 20 July 2022,
how many of the 15 buildings using its grant-based approach (a) have (i) been approached
to take up and (ii) requested directly commissioned assessments, (b) successfully
procured their own surveyors and fire engineers and (c) have an assessment
underway.
Answer
All the 15 buildings using the grant based approach have been issued grant letters and had initial payments to allow contracts to be placed. All have fire engineers and surveyors working on assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09252 by Shona Robison on 21 July 22, what the expenditure has been on the (a) Cladding Remediation Unit and (b) Single Building Assessment in each year since 2017, broken down by type of spending.
Answer
The Cladding Remediation Unit was set up in June 2021 in the Local Government and Communities Directorate. The expenditure on staff whose primary role is to support the programme is:
a)
Core Scottish Government: 2021 - £241,280.00
Core Scottish Government: 2022 (until July) - £113,635.44
Interim contractors 2021 - £52,938.90
Interim contractors 2022 (until July) - £105,369.00
b) Since the start of the Single Building Assessment programme in June 2021 we have grant funded £432,613.63 to support 12 buildings who are currently undergoing assessment. We have a further £510,553 in committed spend to finish these buildings assessments and support 3 additional buildings in starting their assessments through the grant funding model. We have an additional 29 buildings where we will use procurement functions to hire fire engineers and access contractors to begin assessments.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to S6W-09248 by Shona Robison on 20 July 2022, how many buildings (a) have provided consent and details (i) by and (ii) on or since 20 July 2022 and (b) it requires to provide consent and detail before it will move to the contracting process; what the estimated timescales are for the contracting process; and, when contracting, what it plans to propose as a lead time for surveyors and fire engineers to be on site.
Answer
We have confirmed consent from 26 buildings. We have consent in principle from the homeowners from 29 additional buildings since we invited new buildings into the programme in May 2022. The timescale for the contracting process follows the standard Scottish Government procurement rules. We are aware of the supply chain constraints in this field, which is why are working closely with Royal Institution of Chartered Surveyors and the Institute of Fire Engineers to ensure an appropriate stream of qualified assessors. Time scales for the completion of Single Building Assessments are driven by the complexity of the building and are agreed as part of the normal contracting process.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Friday, 05 August 2022
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09619 by Shona Robison on 19 July 2022, whether it will (a)
compile and (b) require local authorities to compile this information to
establish (i) the progress being made to remediate buildings, and (b) how much
remediation is being conducted (A) with the support of the Scottish Government
and (B) privately.
Answer
As the programme progresses, we will gather information from our Single Building Assessments to compile a register of buildings that have been assessed through the programme. Local Authorities will be asked to provide relevant information.
We are currently working with 7 buildings to finalise assessments ahead of remediation. We have asked developers, as part of the Scottish Safer Buildings Accord, to supply data on work that is being undertaken and privately agreed between residents and developers.
- Asked by: Mark Griffin, MSP for Central Scotland, Scottish Labour
-
Date lodged: Monday, 08 August 2022
Submitting member has a registered interest.
-
Current Status:
Answered by Shona Robison on 6 September 2022
To ask the Scottish Government, further to the answer to question S6W-09548 by Shona Robison on 19 July 2022, how much the administrators have been paid to date to administer the loan.
Answer
Since 1 September 2018, the Scottish Government has paid £344,825 to Communities Housing Trust to administer the national Self Build Loan Fund.