- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Thursday, 10 October 2002
-
Current Status:
Answered by David Steel on 29 October 2002
To ask the Presiding Officer whether any estimate has been made of the costs to the Holyrood project in the event that the "degree of uncertainty" referred to by the Holyrood Project Director at the Finance Committee on 8 October 2002 (Official Report, c 2244) results in the new Parliament building not being completed and ready for occupation by December 2003 and, if so, whether the Scottish Parliamentary Corporate Body will give a detailed breakdown of this estimate.
Answer
The Convener of the Holyrood Progress Group has confirmed that no estimates for such an outcome are available at this stage, and as was reported to the Finance Committee at their meeting on 8 October 2002, once the position on programme is more certain, any financial implications will be reported to the committee.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Friday, 11 October 2002
-
Current Status:
Answered by David Steel on 29 October 2002
To ask the Presiding Officer whether there is any conflict of interest between the Parliament and Bovis Lend Lease(Scotland) Ltd in relation to the Holyrood Project.
Answer
No.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Wednesday, 02 October 2002
-
Current Status:
Answered by David Steel on 29 October 2002
To ask the Presiding Officer, further to his answer to question S1W-29132 on 24 September 2002, what the (a) names are of the contractors for the 16 works packages let as part of the Holyrood project where a performance bond is outstanding and (b) total value was of the package awarded to each of these contractors and whether there will be any claim or possible claim in relation to the eight packages let as part of the Holyrood project where a performance bond is no longer required.
Answer
Negotiations on Trade Contracts for the new Scottish Parliament building at Holyrood are carried out on a commercially confidential basis and it would not be appropriate to name publicly those contractors who have yet to provide a Performance Bond, particularly as most contracts in this category have only recently been awarded. The Convener of the Holyrood Progress Group has informed me that there are currently no claims under consideration relating to those Trade Contracts where a Performance Bond is no longer required.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Wednesday, 02 October 2002
-
Current Status:
Answered by David Steel on 29 October 2002
To ask the Presiding Officer, further to his answer to question S1W-29132 on 24 September 2002, how many works packages were let as part of the Holyrood project; what other mechanism, other than a performance bond, was sought and in respect of which works packages; whether a parent company guarantee was used and, if so, in respect of which package, and what the value of each contract was.
Answer
To date, a total of 60 Trade Package contracts have been awarded. Other than a Performance Bond, the SPCB is entitled, under the terms of each contract, to request a Parent Company Guarantee as advised by the Construction Manager. In addition, there are a number of performance management tools in place throughout all Trade Packages which ensure that the client's interests are suitably protected. These are:1. The Construction Managers monitor on a daily basis that work is being carried out to the required standard set out in the detailed specification for materials and workmanship, and performance delivery is measured against the construction programme.2. Action is taken as necessary to ensure that no payment for sub-standard work is made and steps are taken to encourage improved levels of performance.3. Three per cent of the gross value of all payments due to contractors is retained and released only when the client is satisfied that the contract has been completed and any defects rectified to the required standard. To date, with the exception of the contract with Flour City Architectural Metals (UK) Ltd, no recovery has been sought against a Parent Company Guarantee in relation to any of the Trade Packages let. The value of the original contract with Flour City Architectural Metals (UK) package was £7,157,281.29.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Monday, 07 October 2002
-
Current Status:
Answered by Elaine Murray on 28 October 2002
To ask the Scottish Executive whether it is still considering the establishment of a school sport alliance; what the reasons are for its position on this matter, and when it will make an announcement on the issue.
Answer
I refer the member to the answer given to question S1W-26945 on 4 July 2002. All answers to written parliamentary questions are available on the Parliament's website, the search facility for which can be found at
http://www.scottish.parliament.uk/webapp/search_wa.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Tuesday, 08 October 2002
-
Current Status:
Answered by Ross Finnie on 28 October 2002
To ask the Scottish Executive what the cost of the Water Industry Commissioner for Scotland and his department has been since inception.
Answer
The office of the Water Industry Commissioner for Scotland is funded through a levy on Scottish Water. The levy from Scottish Water including establishment costs of the Water Industry Commissioner's office has been £5,170,599 covering the period from 1 November 1999 to March 2003.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Tuesday, 08 October 2002
-
Current Status:
Answered by Ross Finnie on 28 October 2002
To ask the Scottish Executive whether there should be further relaxations to the 20-day standstill rule on livestock movements; whether the detailed risk assessment and wide ranging cost-benefit analysis as recommended in Foot and Mouth Disease 2001: Lessons to be Learned Inquiry has been completed, and whether any measures will be introduced regarding the 20-day rule in the current year.
Answer
The Scottish Executive has no immediate plans to revise the current interim movement regime. The present arrangements will be reviewed with industry stakeholders once the results of the detailed veterinary risk assessment and associated cost-benefit analysis, as recommended by the Lessons to be Learned Inquiry, are known. Findings from these studies will be available in the New Year.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Monday, 07 October 2002
-
Current Status:
Answered by Elaine Murray on 24 October 2002
To ask the Scottish Executive what plans it has to continue funding for the Scottish Teacher Release Scheme should funding for that scheme expire and what its position is on the need to ensure that teachers who participate in the scheme can continue to be released from their duties in order to ensure that children are able to participate in their chosen sport.
Answer
The Teacher Release Scheme operated by sportscotland is in the final year of a three year funding commitment. Sportscotland will be reviewing the scheme in consultation with interested parties over the next few months.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Monday, 07 October 2002
-
Current Status:
Answered by Elaine Murray on 24 October 2002
To ask the Scottish Executive when sportscotland will next meet the Scottish School Sports Federation.
Answer
This is an operational matter for sportscotland. However, I understand that sportscotland has arranged to meet Federation representatives tomorrow.
- Asked by: Fergus Ewing, MSP for Inverness East, Nairn and Lochaber, Scottish National Party
-
Date lodged: Monday, 07 October 2002
-
Current Status:
Answered by Elaine Murray on 24 October 2002
To ask the Scottish Executive whether it will recommend to sportscotland that it should, in consultation with the appropriate representative sport associations in Scotland and Ireland, seek to form an international federation that would permit an annual shinty/hurley fixture between Scotland and Ireland to be acknowledged and recognised as an international fixture.
Answer
It is not part of sportscotland's responsibilities to seek to establish international sporting federations. Shinty/hurling is not a single sport: the annual shinty/hurling fixture is a one-off hybrid event played under composite rules. So far as shinty is concerned, it would be for the Camanachd Association to seek to identify other countries where shinty is played and then explore with interested parties there the formation of an international governing body for the sport.