- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Friday, 14 February 2020
-
Current Status:
Answered by Michael Matheson on 5 March 2020
To ask the Scottish Government how much it has invested in the Highland mainline in each of the last five years.
Answer
The Scottish Government has invested £57 million on major projects on the Highland Mainline over the last 5 years. This investment will contribute to our aspiration of a ten minute average journey time reduction between Inverness and the Central Belt.
The Scottish Government has also invested £2.2 million in other works along the route, including improving accessibility at both Aviemore and Pitlochry Stations.
A breakdown of the £57 million project spend is as follows:-
Financial Year | HML Project Spend |
---|
2015/2016 | £4 million |
2016/2017 | £2 million |
2017/2018 | £5 million |
2018/2019 | £36 million |
2019/2020 | £10 million |
Total | £57 million |
These improvements to the Highland Mainline are in addition to Scottish Government investment in Network Rail’s day to day running (operations, maintenance and renewal) of the route. Network Rail’s performance and funding requirements are set and monitored by the Office of Rail and Road.
Financial Year | Network Rail HML OM&R Spend |
---|
2014/2015 | £ 8 million |
2015/2016 | £ 15 million |
2016/2017 | £ 11 million |
2017/2018 | £ 13 million |
2018/2019 | £ 14 million |
Total | £ 61 million |
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Friday, 14 February 2020
-
Current Status:
Answered by Michael Matheson on 5 March 2020
To ask the Scottish Government what discussions it has had with Network Rail regarding the impact of flooding on the Highland mainline.
Answer
The Office of Rail and Road is responsible for ensuring that Network Rail meets its performance requirements, including resilience.
Transport Scotland meets regularly with the Office of Rail and Road and Network Rail to monitor performance and resilience across the rail network in Scotland, including the Highland Mainline.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 04 March 2020
-
Current Status:
Taken in the Chamber on 12 March 2020
To ask the Scottish Government what discussions it has had regarding the proposed privatisation of the new merged college on Shetland.
Answer
Taken in the Chamber on 12 March 2020
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Monday, 24 February 2020
-
Current Status:
Answered by Mairi Gougeon on 4 March 2020
To ask the Scottish Government when it will publish its conclusions on the Scottish Natural Heritage and Joint Nature Conservation Committee report, Final advice and recommendations on a network of proposed marine Special Protection Areas, which was published on 6 December 2018.
Answer
Following publication of the final advice and recommendations on a network of proposed marine Special Protection Areas by Scottish Natural Heritage (SNH) and Joint Nature Conservation Committee (JNCC) the Scottish Government undertook further public consultation in summer of 2019 in order to complete the Strategic Environmental Assessment (SEA) of the proposed plan. The updated SEA proposed that the Scottish Government should follow the final advice from SNH and JNCC. Ministers are considering all of the scientific evidence underpinning the proposals and will make a decision in due course.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 26 February 2020
-
Current Status:
Taken in the Chamber on 4 March 2020
To ask the Scottish Government what analysis it has carried out of the impact on communities of any reduced levels of council services.
Answer
Taken in the Chamber on 4 March 2020
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 08 January 2020
-
Current Status:
Answered by Roseanna Cunningham on 16 January 2020
To ask the Scottish Government whether Scottish Water is expected to meet the capital expenditure for the period 2015-21 that was agreed prior to that period commencing, and whether it considers that all the capital projects planned at the outset for the period for delivery within 2015-21 are capable of being delivered for the capital expenditure allowed.
Answer
Prior to the start of the 2015-21 regulatory period Scottish Water published its Delivery Plan setting out how it would deliver Ministers Objectives within the financing set out in the independent economic regulator’s Final Determination. Prior to each financial year Scottish Water publishes a Delivery Plan update. In its most recent update, in March 2019, Scottish Water stated that it is “continuing to outperform the challenging financial limits set out in the Final Determination 2014” and ”forecasting a closing cash balance for this period in the range of £60m to £160m once allowance is made to complete the SR15 financed investment”.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 08 January 2020
-
Current Status:
Answered by Roseanna Cunningham on 16 January 2020
To ask the Scottish Government, further to the answer to question S5W-26535 by Roseanna Cunningham on 9 December 2019, what the estimated expenditure is to complete (a) the Amlaird and Corsehouse strategic mains project from the September 2019 date referred to and (b) phase three of the wider Ayrshire Resilience Scheme.
Answer
The estimated expenditure to complete the Amlaird and Corsehouse strategic mains project from September 2019 is £0.7m. The estimated expenditure to complete phase three of the wider Ayrshire Resilience Scheme is £69m-£83m.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 08 January 2020
-
Current Status:
Answered by Roseanna Cunningham on 16 January 2020
To ask the Scottish Government, further to the answer to question S5W-26120 by Roseanna Cunningham on 13 November 2019, whether the sums referred to as being reconciled on a regulatory accounting basis exclude any other capital expenditure incurred by Scottish Water in the period and which may not fall within the definition of "reconciled on a regulatory accounting basis".
Answer
No, the sums provided in the previous response to S5W-26120 as being ‘reconciled on a regulatory accounting basis’ do not exclude any other capital expenditure incurred by Scottish Water in each period.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 08 January 2020
-
Current Status:
Answered by Roseanna Cunningham on 15 January 2020
To ask the Scottish Government how much a 1% increase in water charges raises from (a) household and (b) business customers.
Answer
Scottish Water’s latest published annual accounts are for 2018-19. These report revenue from households of £881.7m and wholesale revenue associated with businesses of £323.6m. Based on these figures a 1% increase in charges would generate an additional £12m overall, of which £8.8m would come from households and £3.2m from wholesale charges.
- Asked by: Rhoda Grant, MSP for Highlands and Islands, Scottish Labour
-
Date lodged: Wednesday, 08 January 2020
-
Current Status:
Answered by Roseanna Cunningham on 15 January 2020
To ask the Scottish Government where the Water Industry Commission for Scotland reports Scottish Water's performance against the tramlines set in the determination of charges for the period 2015-21.
Answer
The Commission reports on Scottish Water’s overall performance against the tramlines and other key elements of the final determination in its annual Performance reports at https://www.watercommission.co.uk/view_Performance%20reports.aspx .
In addition to financial ratios, the Commission examines actual and forecast cash outperformance for the regulatory control period. Scottish Water reports its actual performance in its commentary to the regulatory accounts, which is published on the Commission’s website (see https://www.watercommission.co.uk/UserFiles/Documents/M%20Tables%20commentary%202019.pdf ) and its forecast cash balances which it publishes in its annual Delivery Plan update (see https://docs.google.com/viewerng/viewer?url=www.scottishwater.co.uk/-/media/ScottishWater/Document-Hub/Key-Publications/Delivery-and-Business-Plans/1604192019DeliveryPlanUpdateVersionForPublication.pdf ).