- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it has (a) sought and (b) received advice from the Office of the Scottish Charity Regulator (OSCR) on the proposed new private sector charity that will be part of future design-build-finance-maintain capital projects and what the dates are of all its (i) meetings and (ii) communications with OSCR.
Answer
Scottish Futures Trust is leading work on the creation of a new charity that will form part of the structure of future hub infrastructure projects, seeking advice when required including ongoing engagement with the Office of the Scottish Charity Regulator with which it met on 16 July 2015.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the board of the Scottish Futures Trust's revised design-build-finance-maintain structure will be under private sector control.
Answer
The board of the hub design-build-finance-maintain project companies has always been privately controlled with strong public sector representation. The revised structure seeks to reinforce that position under the new Eurostat guidance.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government what the (a) construction costs and (b) repayment terms are for each capital project, broken down by (i) time period, (ii) annual revenue repayments and (iii) total revenue repayment over the project lifetime.
Answer
Information relating to those projects which are operational or in construction and which form part of the Scottish Government’s current revenue funded non-profit distribution/hub investment programme is available on the Scottish Government’s website:
www.gov.scot/Topics/Government/Finance/18232/12308
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether immediate hub design-build-finance-maintain projects will be signed under the existing structure and transferred to the new structure at a later date, and what the implications are of doing this.
Answer
The intention is that any projects that sign under the existing structure including Forfar Academy and Anderson High would transfer to the new structure at a later date.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the Scottish Futures Trust's proposed model for design-build-finance-maintain projects will have an impact on so-called soft services.
Answer
Soft services, such as cleaning, catering etc, have always been excluded from all non-profit distributing and hub design-build-finance-maintain projects to increase flexibility and learn lessons from the past. There will be no change in any revised structure.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether the Scottish Futures Trust's revised structure for design-build-finance-maintain projects gives a more direct and greater share of each project to the private sector and, if so, for what reason.
Answer
I refer the member to the answer to question S4W-26455 on 31 July 2015. All answers to written parliamentary questions are available on the Parliament’s website, the search facility for which can be found at:
www.scottish.parliament.uk/parliamentarybusiness/28877.aspx.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government which capital projects that were expected to have a financial close in (a) March, (b) April, (c) May, (d) June and (e) July 2015 now have a revised close date due to the changes to the Eurostat designation of capital projects and what the revised dates are.
Answer
At the start of the year, it was anticipated that the following projects would reach financial close as set out in the following table:
| Month | Project |
| January | Forfar Academy |
| February | Inverclyde Health Centre, Baldragon Academy |
| March | NHS Lothian Bundle, Newbattle High School, Anderson High School, Kelso High School, Elgin High School |
| April | - |
| May | - |
| June | Barrhead High School, Our Lady and St Patricks High School |
Forfar Academy reached financial close in June 2015 following completion of an early construction works package and the Anderson High School is due to reach financial close shortly. Other projects have been delayed by a combination of changes to Eurostat guidance and project specific issues. It is too early to provide revised dates for reaching financial close.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government whether it will publish the advice that it has received from Pinsent Masons about the new design-build-finance-maintain capital projects model.
Answer
Legal advice was provided by Pinsent Masons to the Scottish Futures Trust and the hub programme public bodies on a confidential basis.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government what its position is on the Office for National Statistics classification that the non-profit distributing model is a public-private partnership.
Answer
The non-profit distributing model is a form of public-private partnership that has been designed to deliver better value for money to the public sector and the taxpayer than previous public-private partnership/private finance initiative deals. This has always been the case.
- Asked by: Jackie Baillie, MSP for Dumbarton, Scottish Labour
-
Date lodged: Friday, 03 July 2015
-
Current Status:
Answered by John Swinney on 31 July 2015
To ask the Scottish Government what costs have been incurred as a result of the changes to the Eurostat designation of capital projects for additional (a) advice and consultancy, (b) civil service time, (c) Scottish Futures Trust staff time and (d) project/inflation costs.
Answer
Work by Scottish Government and Scottish Futures Trust staff in response to changes in relevant EU guidance has been undertaken within existing resources. The project cost and inflation impact of changes to Eurostat guidance is not yet apparent.