Skip to main content

Language: English / Gàidhlig

Loading…

Seòmar agus comataidhean

Question reference: S6W-28537

  • Date lodged: 15 July 2024
  • Current status: Answered by Fiona Hyslop on 7 August 2024

Question

To ask the Scottish Government, regarding the advanced works for the dualling of the A9 between Tomatin and Moy; whether it will specify what upgraded active travel works have been undertaken, what the total cost was for this work, what consultation it undertook, whether this work has been completed, and, if this is not the case, when it anticipates that this work will be completed. 


Answer

It is important to recognise that the dualling of the A9 between Tomatin and Moy and indeed, the whole A9 dualling programme seeks to enhance journey reliability and safety for all road users, including pedestrians, cyclists, and bus and coach passengers, as well as vehicle drivers and passengers. The design of each project builds in these elements, for example, the provision of new bus stops is integral to the contract for the Tomatin to Moy section.

The advance works listed in the response to S6W-28536 on 7 August 2024 include the following elements of work that will make improvements for pedestrians, cyclists, and bus and coach passengers.

? Tomatin Distillery Access and Local Road Improvements Project:

This advance works contract provided new facilities for pedestrians, cyclists, and bus and coach passengers to facilitate more reliable and safer travel in the area. This included footpaths, a new footbridge which replaced an existing footbridge over All na Frithe watercourse, and new bus stops and bus shelters. Public lighting was also provided along the new footpaths. These enhancements were completed in autumn 2022.

? Lynebeg Railway Underbridge:

This advance works contract included the provision of a new bus lay-by and bus shelter, and associated sections of new footpath, to provide better facilities for pedestrians and bus and coach passengers. This enhancement was completed in Spring 2022.

The cost information available does not enable a breakdown of costs to be provided for each of these measures included in these advance works contracts.

These works have been delivered early as part of the advanced works contracts for the A9 Dualling: Tomatin to Moy project, which was the subject of statutory consultation following publication of draft Orders and the Environmental Statement on 18 May 2018. Prior to that date, consultations on developing proposals were undertaken with a number of individuals and organisations and those findings helped to inform the nature of and design of the measures set out above that have been undertaken to improve reliability and safety for pedestrians, cyclists and bus and coach passengers who travel on this section of the A9.

All answers to written Parliamentary Questions are available on the Parliament's website, the search facility for which can be found at https://www.parliament.scot/chamber-and-committees/written-questions-and-answers .