Skip to main content

Language: English / Gàidhlig

Loading…

Seòmar agus comataidhean

Question reference: S6W-12140

  • Date lodged: 9 November 2022
  • Current status: Answered by Jenny Gilruth on 10 November 2022

Question

To ask the Scottish Government when a decision will be made on the A9 Dualling Killiecrankie to Glen Garry scheme, following the public local inquiry that was held to consider objections received.


Answer

Following careful consideration of the Reporter’s findings, conclusions and recommendations, I have determined that the Orders for the A9 Dualling Killiecrankie to Glen Garry scheme should be made. A decision letter in relation to the Orders is being issued today to all those who made representations to the draft Orders. I want to thank everyone who did so and give an assurance that those representations have been carefully considered.

This significant decision now clears the way for publication of the Made Orders for this scheme. Subject to there being no challenge to Made Orders, we will then be in a position to complete the statutory process for the scheme and acquire land required to build it.

This significant milestone for our ambitious programme to dual the A9 between Perth and Inverness means that 92% of the programme now has Ministerial decisions to make Orders and complete the statutory process.

Road users on the A9 are already benefitting from the dualled stretches between Kincraig and Dalraddy and Luncarty and Pass of Birnam, which opened in September 2017 and August 2021, respectively. Procurement for award of the construction contract for the section between Tomatin and Moy, which will be subject to our normal tender evaluation and business case approval processes, is underway. I expect to be able to update Parliament shortly on the progress of this section.

When completed the A9 Dualling programme will bring many benefits to local communities, businesses, visitors and road users living, travelling and working along the corridor including reduced journey times, improved journey time reliability, improved road safety and opportunities for active travel.