Current status: Answered by Shona Robison on 5 September 2016
To ask the Scottish Government how much will be invested in major NHS projects in each of the next four years.
At this stage, the NHS capital budget is not known beyond 2016-17, therefore there is an element of uncertainty as to what major NHS projects will be undertaken over the next four years.
NHS capital projects in development (with a capital value over £5 million) are listed below along with the expected cost and estimated completion date. The various projects have been grouped into Public Capital, Non-Profit Distribution (NPD) and Revenue financed Hub investments. Major capital projects usually span more than one financial year, therefore the expected completion date is noted below. It should also be noted that the completion date is an estimate which may be subject to change.
NHS boards have also submitted a number of projects to the NHS Capital Investment Group (CIG) for consideration and these projects are progressing through the business case approval process. However until the CIG approve a business case, it will not be included as a planned investment.
Public Capital
NHS Ayrshire and Arran – Building for Better Care (£28 million), Completion expected 2017
NHS Grampian – Baird Family Hospital and ANCHOR Centre (£145 million), Timescales TBC
NHS Highland - Raigmore Critical Care and Theatres (£29 million), Completion expected 2019
NHS Lanarkshire - Monklands Hospital Theatres and ICU (£20 million), Completion expected 2018
NHS Western Isles - St Brendans Hospital (circa £9 million), Timescales TBC
Scottish Ambulance Service - Fleet Replacement for period 2016/2021 (circa £80 million), Ongoing
NHS Scotland – Elective centres (circa £200 million), Timescales TBC
NPD
NHS Ayrshire and Arran - Acute Mental Health and North Ayrshire Community Hospital (£55 million), Completion expected 2016
NHS Dumfries and Galloway - Dumfries and Galloway Royal Infirmary (£274 million), Completion expected 2018
NHS Lothian - Royal Hospital for Sick Children / Department of Clinical Neurosciences (£230 million), Completion expected 2017
NHS Orkney - New Balfour Hospital (£67 million), Completion expected 2018
National Services Scotland - Scottish National Blood Transfusion Service National Centre (£38 million), Completion expected 2017
Revenue-financed Hub projects
NHS Forth Valley – Stirling Care Village (circa £35 million), Completion TBC.
NHS Grampian - Inverurie Health and Care Hub (£14 million), Completion expected 2018
NHS Grampian - Foresterhill Campus - Foresterhill Health Centre (£8 million), Completion expected 2018
NHS Grampian - Primary Healthcare Priorities in Grampian (£19 million), Completion TBC
NHS Greater Glasgow and Clyde – Maryhill and Eastwood Health Centres (£25 million), Completion expected 2016
NHS Greater Glasgow andClyde – Gorbals and Woodside Health Centres (circa £33 million), Completion expected 2017
NHS Greater Glasgow andClyde – Inverclyde Continuing Care for Adults and Older People (£8.5 million), Completion expected 2017
NHS Greater Glasgow and Clyde – Clydebank and Greenock Health Centres (circa £38 million), Completion expected 2019
NHS Highland - Community Hospitals for Skyle, Lochalsh and South West Ross and Badenoch and Strathspey (circa £30 million), Timescales TBC
NHS Lothian – Partnership Centres – Blackburn, NW Edinburgh, Firhill (circa £25 million), Completion expected 2018
NHS Lothian – East Lothian Community Hospital (circa £72 million), Completion expected 2020
NHS Lothian - Royal Edinburgh Campus Redevelopment (Phase 1 £49 million, further phases circa £120 million), Phase 1 expected completion 2016, further phases TBC
NHS Tayside - NHS Scotland Pharmaceuticals Specials Service (£26 million), Timescales TBC
NHS Tayside - Dundee Community Care (circa £20 million), Timescales TBC