Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
Finally—
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
I have another follow-up question. You said that the UK Government had rejected the proposition in the House of Lords to give Ofgem a statutory responsibility to achieve net zero. Given that decarbonising energy is essential to achieving net zero—and that achieving net zero is essential to tackling climate change—why would you not? It would be quite helpful if you could give us, on the record, your rationale for currently rejecting that amendment.
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
I will not refer to that.
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
You said that electricity market arrangements are not glamorous, but I agree that they are essential. Will you set out what you see as the key risks to infrastructure investment of the current electricity market arrangements?
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
My next question leads on from that. What are the expected timescales for the completion and implementation of that transmission network systems change and for your review of the electricity market arrangements?
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
You walked into that, minister.
The issue of competitive advantage is key. We have world-leading skills and experience. Scotland has fantastic renewables opportunities in terms of the pwer that can be generated from the wind, although it is not being serviced properly by the grid. However, one thing that will not be competitive is transmission charges for the generators. When we know that we face increasing competition coming at us from elsewhere, we have to take advantage of the window of opportunity, but uncompetitive transmission charges for our generators are a real disincentive to investment. What can be done about that? What has been done more recently? Do you recognise that the generation of renewable energy in Scotland is at a severe disadvantage to that elsewhere in the UK and the rest of Europe?
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
So, it becomes an argument whether it is in the interests of consumers to have renewable energy—full stop.
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
I am sure that you are, but the Treasury is making the decisions. What does it need to speed up its decision making?
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
We are suggesting that seeking consent with regard to devolved areas instead of just consulting would make a big difference.
Net Zero, Energy and Transport Committee
Meeting date: 27 April 2023
Fiona Hyslop
I want to press you on your decision making. Once you have the recommendations, what do you see as being a successful timescale for making decisions that will make a difference? The risks are very high.