Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
Why did it not happen?
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
Were you happy to accept that at the time?
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
That is what you do.
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
You disagree with that.
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
I might come back to more questions on that later on.
How fit for purpose is the current ferry procurement process in Scotland, and how does it compare with processes in other countries? That question is based on previous evidence that we have had. We are now procuring ferries from Turkey, but the ferries that we have procured are double the price that Norway is paying.
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
Section 6.9 of your submission states:
“CMAL were told that they should not seek a Ministerial direction by the Ministers in relation to contract award of the Vessels to FMEL. However, the Board were sufficiently concerned about the Contracts in all the circumstances instead to seek a letter from the Ministers holding CMAL harmless in the event that the Contracts encountered the financial and technical issues identified in the risks paper.”
At that point, you seemed very, very concerned. I still do not understand why CMAL did not just go in and cancel the contract.
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
Therefore, you were told to go in—
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
I have a question about the ports. The two ferries that are coming into service run on diesel and liquefied natural gas. Has work started on the bunkering facilities to store that? It has also been commented on that the vessels are larger than the ones that are currently in operation, so the ports are too short to take them. Again, has work started in that regard?
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
Are they expected to be completed by the time the vessels come into operation?
Public Audit Committee
Meeting date: 30 June 2022
Sharon Dowey
Section 3 of your submission is on “Provision of Refund Guarantees”. In section 3.6, you state that
“CMAL had no awareness of, or involvement in, these exchanges.”
That was in reference to exchanges between MSPs and so on about the non-provision of the refund guarantee from Ferguson Marine Engineering Ltd. When did you find out that FMEL was not giving the builders refund guarantee and why did you not go back to the tendering process at that point?