Skip to main content
Loading…

Seòmar agus comataidhean

Official Report: search what was said in Parliament

The Official Report is a written record of public meetings of the Parliament and committees.  

Criathragan Hide all filters

Dates of parliamentary sessions
  1. Session 1: 12 May 1999 to 31 March 2003
  2. Session 2: 7 May 2003 to 2 April 2007
  3. Session 3: 9 May 2007 to 22 March 2011
  4. Session 4: 11 May 2011 to 23 March 2016
  5. Session 5: 12 May 2016 to 5 May 2021
  6. Current session: 12 May 2021 to 5 July 2025
Select which types of business to include


Select level of detail in results

Displaying 1158 contributions

|

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 8 September 2022

Sharon Dowey

So you were not aware of that prior to the contract being awarded.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 8 September 2022

Sharon Dowey

Okay.

Public Audit Committee

Major Capital Projects

Meeting date: 30 June 2022

Sharon Dowey

I will try to keep my question short. It is specifically about a road that goes through my area, the A77. You mentioned that we have just had the Maybole bypass put in, which is great. It has a couple of passing points, but it is not a dual carriageway. The A77 is a main route from Scotland to Northern Ireland and it is a single carriageway for the majority of the way from Ayr down to Cairnryan, with the exception now of a few passing places on the Maybole bypass. When you are deciding on major capital projects, what consideration is given to spreading the allocation of funding around the country—to south-west Scotland, for example—with environmental targets having an impact on road investment?

You talked about reviewing work that is being carried out. How often are those reviews carried out? At the moment, the A77 at the Carlock wall is not even a single carriageway—it is down to one lane, and there are traffic lights that have been there for nearly three years.

Public Audit Committee

Major Capital Projects

Meeting date: 30 June 2022

Sharon Dowey

How often do you review the projects? The Carlock wall scheme has now been going on for three years, and a main transport route is down to a single lane.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

When you found out that it was not going to give you the builders refund guarantee, which was part of the tendering process, why did you not cancel the contract at that point and go back to the tendering process? In the communication that you have sent through, that seemed to be your preferred choice.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Section 6.9 of your submission states:

“CMAL were told that they should not seek a Ministerial direction by the Ministers in relation to contract award of the Vessels to FMEL. However, the Board were sufficiently concerned about the Contracts in all the circumstances instead to seek a letter from the Ministers holding CMAL harmless in the event that the Contracts encountered the financial and technical issues identified in the risks paper.”

At that point, you seemed very, very concerned. I still do not understand why CMAL did not just go in and cancel the contract.

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Therefore, you were told to go in—

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

I have a question about the ports. The two ferries that are coming into service run on diesel and liquefied natural gas. Has work started on the bunkering facilities to store that? It has also been commented on that the vessels are larger than the ones that are currently in operation, so the ports are too short to take them. Again, has work started in that regard?

Public Audit Committee

Section 23 Report: “New vessels for the Clyde and Hebrides: Arrangements to deliver vessels 801 and 802”

Meeting date: 30 June 2022

Sharon Dowey

Are they expected to be completed by the time the vessels come into operation?