Question

To ask the Scottish Government whether MV Glen Sannox was completed to its original design specification as stipulated by CMAL.  


Answer

During the build phase of MV Glen Sannox, certain specifications required amendment to ensure compliance with updated regulatory standards issued by the Maritime and Coastguard Agency (MCA). This is standard practice within the shipbuilding industry, where ongoing engagement with the MCA is essential to ensure that vessels meet all necessary safety and operational requirements.