Question reference: S6W-29505

  • Date lodged: 3 September 2024 Registered interest
  • Current status: Answered by Fiona Hyslop on 18 September 2024

Question

To ask the Scottish Government whether it will set out the capital allocation for (a) vessel procurement and (b) harbour infrastructure upgrades in Phase 1 of the Small Vessel Replacement Programme.


Answer

The full costs of the procurement for the seven vessels as part of the Small Vessels Replacement Programme are estimated to be around £175 million including the provision of harbour upgrades and shore power connections.

The split cannot be given at this time given the live procurement of the programme and will only be known following the successful completion of the procurement exercise, anticipated March 2025.