Question reference: S6W-18009

  • Date lodged: 17 May 2023
  • Current status: Answered by Gillian Martin on 23 May 2023

Question

To ask the Scottish Government how much funding has been allocated to the H100 Fife project to date, including through the Scottish Budget 2023-24.


Answer

The use of hydrogen for the provision of domestic heat using the gas network will be demonstrated over the next few years in Scotland as part of the SGN H100 Fife ‘neighbourhood trial’ and in the UK as part of the larger village and town trials. The H100 Fife project is currently under construction, with aims to fit 100% hydrogen boilers into 300 homes in Leven. The project is scheduled to go live in 2024, and operate until March 2027. The Scottish Government has provided £6.9m grant funding to the project.