To ask the Scottish Government, further to the Deputy First Minister's statement to the Parliament on 16 March 2023, whether it will provide a list of the “design gaps and build errors” regarding Hull 801, which were cited as the cause for the further revision to the timescale for delivery of the vessel by Ferguson Marine.


Answer

This is a matter for the CEO of Ferguson Marine Port Glasgow however the Member may wish to note that Ministers are committed to publishing the monthly progress updates on progress with the build of both vessels on the Scottish Government website .